Responsibility assignment matrix
abbr. RAM
Definition
A responsibility assignment matrix lists tasks, work packages or deliverables in rows and roles or people in columns. The cells show which type of involvement applies in each case. The most widely used scheme is RACI: responsible for carrying out the work, accountable for final ownership, consulted for specialist input and informed for being kept up to date.
Equivalents in other frameworks
Concept Assigning responsibilities to tasks · four frameworks reviewed
| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK | Responsibility assignment matrix | equivalent | — |
| PM² | RASCI | closely related | fixed form with the five roles responsible, accountable, supporting, consulted, informed |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |
The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.
All designations of this concept side by side
Comparisons
Other terms
Other words for the same thing in English usage. Not to be confused with the equivalents above, which translate between frameworks.
- RAM
- abbreviation
- RACI matrix
- related, not equivalent
Classification
- this term
- Responsibility assignment matrix
- Topic area
- Project organization
Distinction
The organization chart shows who reports to whom, the responsibility assignment matrix who does what. The work breakdown structure provides the rows, the roles from the organization chart the columns. Variants such as RASCI add further types of involvement, for example supporting roles.
In practice
When a new HR information system is introduced, there is a dispute about who should clean up the master data. The project manager draws up a responsibility assignment matrix for the twenty most important results. It turns out that both the HR department and IT had entered an A for data cleansing. After half an hour of clarification, accountability lies with the HR department and IT is listed as supporting.
Frequently asked questions
How many accountable roles may there be per row?
Exactly one. If two roles are jointly accountable, in case of doubt neither feels responsible.
How detailed should the matrix be?
As coarse as possible and as detailed as necessary. Detail pays off for interfaces and known points of conflict, but usually not for routine tasks.
Source and context
- Reference
- ISO 21506:2024, 3.75
- Edition
- ISO 21506:2024
- Author
- Dennis Hain
Cite this entry
Hain, D. (n.d.). Responsibility assignment matrix. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/responsibility-assignment-matrix/
Hain, D. (n.d.): Responsibility assignment matrix. PMDecoder, entry on ISO 21506:2024, 3.75. https://pmdecoder.com/en/glossary/responsibility-assignment-matrix/ (retrieved 24 November 2026)
@misc{responsibilityassignmentmatrix,
author = {Hain, Dennis},
title = {Responsibility assignment matrix},
note = {PMDecoder, ISO 21506:2024, 3.75},
url = {https://pmdecoder.com/en/glossary/responsibility-assignment-matrix/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/responsibility-assignment-matrix/"> <p>Table that records, for each task or result, which role is accountable, carries it out, contributes or is kept informed.</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/responsibility-assignment-matrix/">Responsibility assignment matrix</a>, PMDecoder, ISO 21506:2024, 3.75</footer> </blockquote>
Found a mistake? Let us know, we check every report.