Logical relationship
also: Precedence relationship
Definition
A logical relationship links a predecessor to a successor and specifies which point in time of the one is tied to which point in time of the other. There are four types: finish-to-start, start-to-start, finish-to-finish and start-to-finish. In addition, a time interval can be specified to express a waiting period or an overlap.
Equivalents in other frameworks
Concept Scheduling dependency between two activities · three frameworks reviewed
| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK | Logical relationship | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |
The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.
Classification
- this term
- Logical relationship
- Narrower terms
- Start-to-start relationshipFinish-to-finish relationshipFinish-to-start relationshipStart-to-finish relationship
- Topic area
- Network planning
Distinction
A dependency describes the underlying reason why activities are connected; the logical relationship is its formal representation in the network schedule. A date constraint ties an activity to a calendar date, not to another activity. In German, the four types are known as Normalfolge, Anfangsfolge, Endfolge and Sprungfolge.
In practice
When a library moves, the planner specifies that packing a stack room must be complete before its transport begins. Setting up the shelves at the new site is to start at the same time as dismantling them at the old one. And the handover of the old building may only finish once cleaning is also complete. These three types of relationship are enough to represent the entire move; a fourth is not needed.
Frequently asked questions
Which logical relationship is the most common?
Finish-to-start. In most schedules it accounts for by far the largest share of links.
What is a time interval in a logical relationship?
A period that must lie between the linked points in time. A positive value means a waiting period, a negative value a permitted overlap.
Source and context
- Author
- Dennis Hain
Cite this entry
Hain, D. (n.d.). Logical relationship. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/logical-relationship/
Hain, D. (n.d.): Logical relationship. PMDecoder. https://pmdecoder.com/en/glossary/logical-relationship/ (retrieved 24 November 2026)
@misc{logicalrelationship,
author = {Hain, Dennis},
title = {Logical relationship},
note = {PMDecoder},
url = {https://pmdecoder.com/en/glossary/logical-relationship/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/logical-relationship/"> <p>Defined time dependency between two activities that determines when one may start or finish in relation to the other</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/logical-relationship/">Logical relationship</a>, PMDecoder</footer> </blockquote>
Found a mistake? Let us know, we check every report.