Project forecast
also: Project forecasting
Definition
A project forecast projects the course so far and what is known about the remaining work into the future. It answers questions such as: When will we finish? What total costs are to be expected? What scope will have been delivered by the deadline? It is based on actual data, estimates of remaining work from those responsible, trends and known risks. Forecasts are updated regularly and compared with the baseline.
Equivalents in other frameworks
Concept Estimate of final dates and costs · one framework reviewed
| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK | Forecast | closely related | can refer to any future quantity, not only the finish date and final cost |
The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.
All designations of this concept side by side
Comparisons
Classification
- this term
- Project forecast
- Topic area
- Monitoring and control
Distinction
The baseline shows what was agreed, the forecast what is likely to happen. An estimate made before the project starts is based on assumptions; a forecast during the project is also based on measured values. Earned value management has defined formulas for forecasts, for example for the expected total costs.
In practice
A research institute forecasts the total costs of a three-year collaborative project every quarter. After the first year, spending is on plan, but the remaining-work estimates of the research groups show that the laboratory experiments will be more expensive than assumed. The forecast rises by eight per cent. The institute applies to the funding body in good time to reallocate funds, instead of having to explain an overrun at the end.
Frequently asked questions
How accurate are project forecasts?
Not very at the start, increasingly so as the project progresses. Honest estimates of remaining work matter more than sophisticated formulas.
How do forecast and plan differ?
The plan is a target, the forecast an expectation. If the two are far apart, a decision is needed.
Source and context
- Author
- Dennis Hain
Cite this entry
Hain, D. (n.d.). Project forecast. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/project-forecast/
Hain, D. (n.d.): Project forecast. PMDecoder. https://pmdecoder.com/en/glossary/project-forecast/ (retrieved 24 November 2026)
@misc{projectforecast,
author = {Hain, Dennis},
title = {Project forecast},
note = {PMDecoder},
url = {https://pmdecoder.com/en/glossary/project-forecast/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/project-forecast/"> <p>Estimate of when a project is likely to finish and what it will cost in total, based on its current status</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/project-forecast/">Project forecast</a>, PMDecoder</footer> </blockquote>
Found a mistake? Let us know, we check every report.