Responsibility assignment matrix
Definition
In PMI usage, the responsibility assignment matrix (RAM) is a grid that assigns project resources to work packages or tasks. The rows usually list elements of the work breakdown structure or individual activities, the columns people, roles or organizational units. The cells show who is involved and in what way. A RAM can link organizational units with work packages at a high level, or individual people with activities at a detailed level. The best-known form is the RACI chart with the roles responsible, accountable, consulted and informed.
Equivalents in other frameworks
Concept Assigning responsibilities to tasks · four frameworks reviewed
| Framework | Term there | Relation | Note |
|---|---|---|---|
| ISO 21506 | Responsibility assignment matrix | equivalent | — |
| PM² | RASCI | closely related | fixed form with the five roles responsible, accountable, supporting, consulted, informed |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |
The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.
All designations of this concept side by side
Comparisons
Classification
- this term
- Responsibility assignment matrix
- Topic area
- Project organization
Distinction
The RAM corresponds to the responsibility assignment matrix in the standard. The RASCI chart in PM² is a specific variant with an additional supporting role. The organizational breakdown structure supplies the organizational units, the work breakdown structure the work packages; the RAM brings both together in one table. An important rule with RACI is that only one person is accountable for each task.
In practice
In a project to introduce a document management system, the project manager sets up a RAM. For the work package “Data migration”, the IT architect is accountable, two developers carry out the work, the data protection officer is consulted and the business units are informed. Going through the table reveals that nobody is accountable for training; this is resolved at the next team meeting.
Frequently asked questions
Is RACI the same as a responsibility assignment matrix?
RACI is a common form of RAM, but not the only one. Organizations also use other codes, for example with additional roles for support or sign-off, or simple crosses to indicate involvement.
How detailed should a RAM be?
Detailed enough for everyone to recognize their tasks and for no gaps to remain. In large projects it is worth having a RAM per level: a high-level one for organizational units and a detailed one within sub-teams.
Source and context
- Reference
- PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition
- PMBOK Guide – Eighth Edition
Cite this entry
Responsibility assignment matrix. (n.d.). In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/responsibility-assignment-matrix-pmi/
Responsibility assignment matrix (n.d.). PMDecoder, entry on PMI Lexicon of Project Management Terms 4.0 (2024). https://pmdecoder.com/en/glossary/responsibility-assignment-matrix-pmi/ (retrieved 24 November 2026)
@misc{responsibilityassignmentmatrixpmi,
title = {Responsibility assignment matrix},
note = {PMDecoder, PMI Lexicon of Project Management Terms 4.0 (2024)},
url = {https://pmdecoder.com/en/glossary/responsibility-assignment-matrix-pmi/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/responsibility-assignment-matrix-pmi/"> <p>Table that links work packages or tasks to people or groups and shows the role each one plays.</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/responsibility-assignment-matrix-pmi/">Responsibility assignment matrix</a>, PMDecoder, PMI Lexicon of Project Management Terms 4.0 (2024)</footer> </blockquote>
Found a mistake? Let us know, we check every report.