Product Description

Definition

In PRINCE2, a product description describes a single product that is to be created in the project. It states its purpose, its components, the sources or earlier products from which it is derived, the format in which it is to be provided and the skills required to produce it. Of particular importance are the quality criteria with their tolerances, the checking methods and the responsibilities for producing, reviewing and approving it. Product descriptions are written during planning as soon as the products are known, and are baselined with the plan concerned. They form part of the work packages and are the basis for quality checks.

Equivalents in other frameworks

Concept Description of work breakdown structure elements · three frameworks reviewed

Equivalents of Product Description in other frameworks
FrameworkTerm thereRelationNote
ISO 21506Work breakdown structure dictionarypartially overlappingDescribes products rather than work and defines quality criteria, checking methods and responsibilities.
PMI / PMBOKWBS dictionarypartially overlappingDescribes products rather than work and defines quality criteria, checking methods and responsibilities.
generalWork package descriptionpartially overlappingdescribes a single work package, not all elements of the work breakdown structure

The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.

All designations of this concept side by side

Classification

this term
Product Description

Distinction

The work breakdown structure dictionary under ISO 21506 describes the elements of the work breakdown structure, which are often pieces of work. The product description, by contrast, describes a result and puts particular emphasis on when it counts as finished and fit for purpose. The project product description is a special form for the overall output of the project.

In practice

For a training project, the product description “Participant handbook” describes the purpose and target group, divides the handbook into six chapters with exercises, names the subject concepts as its source and specifies: no more than 60 pages, understandable without prior knowledge, proofread by two experts and approved by the head of the academy. From the outset, the author knows how her work will be judged.

Frequently asked questions

Does every product need a product description?

Not necessarily. It is useful for all important products and for all products handed over to other teams or suppliers. For simple intermediate products a reference is often enough.

Who writes the product description?

Usually the project manager together with experts and future users. The quality criteria should be shaped by the people who will later approve the product.

Source and context

Reference
PRINCE2 7, Managementprodukte
Edition
PRINCE2 7
Cite this entry
APA

Hain, D. (n.d.). Product Description. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/product-description/

Short form

Hain, D. (n.d.): Product Description. PMDecoder, entry on PRINCE2 7, Managementprodukte. https://pmdecoder.com/en/glossary/product-description/ (retrieved 24 November 2026)

BibTeX
@misc{productdescription,
  author  = {Hain, Dennis},
  title   = {Product Description},
  note    = {PMDecoder, PRINCE2 7, Managementprodukte},
  url     = {https://pmdecoder.com/en/glossary/product-description/},
  urldate = {2026-11-24}
}

Embed this definition

HTML fragment for your own website: short definition with source and link, no script and no tracking.

HTML
<blockquote cite="https://pmdecoder.com/en/glossary/product-description/">
  <p>PRINCE2 management product describing the purpose, composition, quality criteria and checking methods of a single product.</p>
  <footer>Source: <a href="https://pmdecoder.com/en/glossary/product-description/">Product Description</a>, PMDecoder, PRINCE2 7, Managementprodukte</footer>
</blockquote>

Found a mistake? Let us know, we check every report.