Earned value management planning

also: EVM planning

Definition

Before a project can measure earned value, it has to be clear how this will be done. Earned value management planning determines how the work breakdown structure and the organizational breakdown structure are combined into control accounts, how budgets are spread over time, which rules are used to credit progress, how actual costs are captured, and how often and in what format reports are produced. The result is an agreed approach for setting up the performance measurement baseline and following it throughout the project.

Equivalents in other frameworks

No equivalents have been recorded for this term yet.

Classification

this term
Earned value management planning

Distinction

Earned value management planning describes the approach, while the performance measurement baseline is the result against which performance is later measured. It differs from general cost planning in that it explicitly links scope, schedule and costs and makes the rules for measuring progress binding in advance.

In practice

A regional transport association starts introducing a new ticketing system with a budget of twelve million euros. In the first six weeks, the project office decides that 22 control accounts will be created at the third level of the work breakdown structure, that software packages will be credited by milestones and hardware deliveries under the 0/100 rule, and that actual costs will be taken from the ERP system every week. Only then is the baseline frozen and the first monthly report produced.

Frequently asked questions

When does earned value management planning take place?

At the start, before the baseline is approved. It is reviewed and adjusted whenever the project changes significantly.

Does every project have to produce its own plan?

Organizations that run many projects with this method often record the basic rules in a procedure. The individual project then only specifies what deviates from it or needs to be made more concrete.

Source and context

Reference
ISO 21506:2024, 3.23
Edition
ISO 21506:2024
Cite this entry
APA

Hain, D. (n.d.). Earned value management planning. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/earned-value-management-planning/

Short form

Hain, D. (n.d.): Earned value management planning. PMDecoder, entry on ISO 21506:2024, 3.23. https://pmdecoder.com/en/glossary/earned-value-management-planning/ (retrieved 24 November 2026)

BibTeX
@misc{earnedvaluemanagementplanning,
  author  = {Hain, Dennis},
  title   = {Earned value management planning},
  note    = {PMDecoder, ISO 21506:2024, 3.23},
  url     = {https://pmdecoder.com/en/glossary/earned-value-management-planning/},
  urldate = {2026-11-24}
}

Embed this definition

HTML fragment for your own website: short definition with source and link, no script and no tracking.

HTML
<blockquote cite="https://pmdecoder.com/en/glossary/earned-value-management-planning/">
  <p>Preparatory planning that sets out how a project builds its measurement of performance: baseline, crediting rules, responsibilities and reports.</p>
  <footer>Source: <a href="https://pmdecoder.com/en/glossary/earned-value-management-planning/">Earned value management planning</a>, PMDecoder, ISO 21506:2024, 3.23</footer>
</blockquote>

Found a mistake? Let us know, we check every report.