Undistributed budget
abbr. UB
Definition
Undistributed budget arises when work has been approved but it is not yet settled which control accounts will take it on, for example immediately after an agreed extension of scope. The budget already belongs to the performance measurement baseline but is not yet measured, because it has not been tied to any scheduled work content. It should be distributed as soon as possible so that the new work can be planned and monitored.
Equivalents in other frameworks
No equivalents have been recorded for this term yet.
Classification
- this term
- Undistributed budget
- Topic area
- Monitoring and control
Distinction
The management reserve lies outside the performance measurement baseline and is intended for the unforeseen. Undistributed budget lies inside the baseline and belongs to work that is already known and approved but not yet planned in detail. It has nothing to do with unspent budget, meaning money left over at the end.
In practice
During an ongoing development project, an automotive supplier is commissioned to develop an additional connector variant and receives 350,000 euros more for it. On the day the contract is amended, the amount is added to the baseline as undistributed budget. Over the next three weeks, design and testing plan the work packages; the project manager then allocates 330,000 euros to two control accounts and holds back 20,000 euros for tests still to be defined, which are assigned the following month.
Frequently asked questions
How long may budget remain undistributed?
Only briefly, if possible. Many organizations stipulate that it must be allocated to control accounts within one or two reporting periods.
Is undistributed budget included in the figures?
It only enters planned value once it has been distributed and scheduled. It is, however, already part of the budget at completion for the project as a whole.
Source and context
- Reference
- ISO 21506:2024, 3.92
- Edition
- ISO 21506:2024
- Author
- Dennis Hain
Cite this entry
Hain, D. (n.d.). Undistributed budget. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/undistributed-budget/
Hain, D. (n.d.): Undistributed budget. PMDecoder, entry on ISO 21506:2024, 3.92. https://pmdecoder.com/en/glossary/undistributed-budget/ (retrieved 24 November 2026)
@misc{undistributedbudget,
author = {Hain, Dennis},
title = {Undistributed budget},
note = {PMDecoder, ISO 21506:2024, 3.92},
url = {https://pmdecoder.com/en/glossary/undistributed-budget/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/undistributed-budget/"> <p>Budget released for approved work that for the time being has not yet been allocated to any control account.</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/undistributed-budget/">Undistributed budget</a>, PMDecoder, ISO 21506:2024, 3.92</footer> </blockquote>
Found a mistake? Let us know, we check every report.