Integrated baseline review

abbr. IBR

Definition

An integrated baseline review takes place once the performance measurement baseline has been set up, and often again after major changes. The client, the project manager and the control account managers work through together whether all of the technical content is covered, whether schedules, budgets and resources fit together and whether risks have been taken into account. The aim is for everyone involved to read the baseline in the same way before variances against it are reported.

Equivalents in other frameworks

No equivalents have been recorded for this term yet.

Classification

this term
Integrated baseline review

Distinction

An audit checks whether processes and requirements are being followed. An integrated baseline review examines the content of a specific plan and ends with jointly agreed actions. It differs from a project approval in that it does not decide whether the project goes ahead but secures the basis for measurement.

In practice

Three months after the contract for a shipbuilding project begins, representatives of the navy and the shipyard meet for a two-day integrated baseline review. Interviews with eight control account managers reveal that the integration of the weapon systems appears in the schedule but has no budget for testing. The shipyard adds a work package and adjusts the baseline before the first formal performance report is issued.

Frequently asked questions

Who takes part in an integrated baseline review?

Representatives of the client, the project manager and the people who own control accounts. Specialists in scheduling, cost and risk often join them.

Is the review only common in public contracts?

It is most widespread in large public programmes that use earned value management, for example in defence and space. The idea of reviewing a baseline jointly before measuring against it can, however, be applied to any larger project.

Source and context

Reference
ISO 21506:2024, 3.30
Edition
ISO 21506:2024
Cite this entry
APA

Hain, D. (n.d.). Integrated baseline review. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/integrated-baseline-review/

Short form

Hain, D. (n.d.): Integrated baseline review. PMDecoder, entry on ISO 21506:2024, 3.30. https://pmdecoder.com/en/glossary/integrated-baseline-review/ (retrieved 24 November 2026)

BibTeX
@misc{integratedbaselinereview,
  author  = {Hain, Dennis},
  title   = {Integrated baseline review},
  note    = {PMDecoder, ISO 21506:2024, 3.30},
  url     = {https://pmdecoder.com/en/glossary/integrated-baseline-review/},
  urldate = {2026-11-24}
}

Embed this definition

HTML fragment for your own website: short definition with source and link, no script and no tracking.

HTML
<blockquote cite="https://pmdecoder.com/en/glossary/integrated-baseline-review/">
  <p>Joint review by client and project team of whether the performance measurement baseline is complete, realistic and understood alike by all.</p>
  <footer>Source: <a href="https://pmdecoder.com/en/glossary/integrated-baseline-review/">Integrated baseline review</a>, PMDecoder, ISO 21506:2024, 3.30</footer>
</blockquote>

Found a mistake? Let us know, we check every report.