Time-phased budget
Definition
A total budget on its own does not say when money will be needed. A time-phased budget therefore specifies which share falls in which month, quarter or phase, in line with the schedule of the work packages. Accumulated over time, this produces a curve that is typically S-shaped. It is the basis for planned value in earned value management and for cash planning.
Equivalents in other frameworks
No equivalents have been recorded for this term yet.
Classification
- this term
- Time-phased budget
- Topic area
- Monitoring and control
Distinction
Planned value is the figure that the time-phased budget yields for a particular cut-off date. The performance measurement baseline is the time-phased budget of the entire project without the management reserve. A cash outflow plan, by contrast, describes when payments fall due, which can differ considerably from when the work is actually performed.
In practice
A university plans to refurbish a lecture hall building over 18 months for 6 million euros. Instead of spreading the budget evenly across the months, the building department follows the schedule: planning and strip-out work account for 400,000 euros in the first three months, and the main trades for 3.6 million euros in months seven to twelve. Only in this way does a comparison with actual progress in month four give a realistic picture.
Frequently asked questions
Why is an even distribution not good enough?
Because projects rarely incur costs evenly. With a linear distribution, a project would appear to be behind at the start and ahead later on.
How finely is the budget distributed?
Usually by reporting period, that is monthly or every four weeks. For later stages a coarser distribution is often sufficient, refined step by step with rolling wave planning.
Source and context
- Reference
- ISO 21506:2024, 3.91
- Edition
- ISO 21506:2024
- Author
- Dennis Hain
Cite this entry
Hain, D. (n.d.). Time-phased budget. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/time-phased-budget/
Hain, D. (n.d.): Time-phased budget. PMDecoder, entry on ISO 21506:2024, 3.91. https://pmdecoder.com/en/glossary/time-phased-budget/ (retrieved 24 November 2026)
@misc{timephasedbudget,
author = {Hain, Dennis},
title = {Time-phased budget},
note = {PMDecoder, ISO 21506:2024, 3.91},
url = {https://pmdecoder.com/en/glossary/time-phased-budget/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/time-phased-budget/"> <p>Budget assigned to the periods or phases in which the work is expected to take place and the costs to arise.</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/time-phased-budget/">Time-phased budget</a>, PMDecoder, ISO 21506:2024, 3.91</footer> </blockquote>
Found a mistake? Let us know, we check every report.