Subnetwork

Definition

A subnetwork contains the activities of a particular area, such as a subproject, a trade, a construction section or a supplier. It can be planned and maintained on its own and is linked to other subnetworks through interface activities or milestones. This keeps large network schedules manageable, and those responsible can work on their part without having to oversee the entire network. Recurring sequences can be reused several times as a template.

Equivalents in other frameworks

No equivalents have been recorded for this term yet.

Classification

this term
Subnetwork

Distinction

A subnetwork is a section by content, whereas a summary activity is a condensed representation in the bar chart. A condensed network combines many activities into a few, while the subnetwork keeps the detail of its section. The interfaces between subnetworks are the points at which delays spread to other areas.

In practice

For a residential development with six identical houses, the site management creates a subnetwork for one house: shell, roof, windows, building services, interior finishing. The template is inserted six times and staggered in time. The subnetworks are linked through the shared crane and the crews that move from house to house. When the shell of the second house is delayed, the overall schedule shows which later houses are affected.

Frequently asked questions

When is it worth creating subnetworks?

For large network schedules, when several units are responsible, and for recurring sequences that can serve as a template.

How are subnetworks linked?

Through shared milestones or interface activities that appear in both subnetworks and whose dates have been agreed.

Source and context

Cite this entry
APA

Hain, D. (n.d.). Subnetwork. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/subnetwork/

Short form

Hain, D. (n.d.): Subnetwork. PMDecoder. https://pmdecoder.com/en/glossary/subnetwork/ (retrieved 24 November 2026)

BibTeX
@misc{subnetwork,
  author  = {Hain, Dennis},
  title   = {Subnetwork},
  note    = {PMDecoder},
  url     = {https://pmdecoder.com/en/glossary/subnetwork/},
  urldate = {2026-11-24}
}

Embed this definition

HTML fragment for your own website: short definition with source and link, no script and no tracking.

HTML
<blockquote cite="https://pmdecoder.com/en/glossary/subnetwork/">
  <p>Section of a network schedule that represents a defined part of the project and is linked to the overall network through interfaces</p>
  <footer>Source: <a href="https://pmdecoder.com/en/glossary/subnetwork/">Subnetwork</a>, PMDecoder</footer>
</blockquote>

Found a mistake? Let us know, we check every report.