Theory of Constraints
abbr. TOC
Definition
The Theory of Constraints goes back to Eliyahu M. Goldratt, who popularised it in the 1980s in the form of a novel. Its basic idea is that every system has at least one constraint that limits its overall performance. Improvements elsewhere achieve little. The approach follows five steps: identify the constraint, exploit it as well as possible, subordinate everything else to it, elevate the constraint and then start again, because a new constraint emerges.
Equivalents in other frameworks
No equivalents have been recorded for this term yet.
Classification
- this term
- Theory of Constraints
- Topic area
- Network planning
Distinction
The critical chain method applies the Theory of Constraints to project management by treating resources as the constraint and pooling buffers. Lean aims to eliminate waste across the entire flow, whereas the Theory of Constraints targets the one limiting point. Resource levelling resolves bottlenecks in the schedule without considering the system as a whole.
In practice
A software department delivers new features too slowly. Instead of hiring more developers, the team analyses the workflow and finds the bottleneck in testing: two testers check the work of twelve developers. Following the Theory of Constraints, testing capacity is first put to better use, for example through automated preliminary checks, and development only works ahead as much as can be tested. The lead time falls without any additional staff being hired.
Frequently asked questions
What is a constraint in a project?
A resource, department or approval body whose capacity limits the speed of the whole, such as a specialist, a test bench or a committee that rarely meets.
Why is it not worth improving everywhere at the same time?
Because improvements outside the constraint do not increase throughput and often only create additional work in progress.
Source and context
- Author
- Dennis Hain
Cite this entry
Hain, D. (n.d.). Theory of Constraints. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/theory-of-constraints/
Hain, D. (n.d.): Theory of Constraints. PMDecoder. https://pmdecoder.com/en/glossary/theory-of-constraints/ (retrieved 24 November 2026)
@misc{theoryofconstraints,
author = {Hain, Dennis},
title = {Theory of Constraints},
note = {PMDecoder},
url = {https://pmdecoder.com/en/glossary/theory-of-constraints/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/theory-of-constraints/"> <p>Management approach holding that a system's performance is determined by its tightest constraint, on which all improvement should focus</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/theory-of-constraints/">Theory of Constraints</a>, PMDecoder</footer> </blockquote>
Found a mistake? Let us know, we check every report.