Parent element
Definition
In a work breakdown structure, every element that has been broken down further is a parent element. It describes part of the scope whose work is entirely contained in its child elements. It has no work of its own that is not included in one of them. The budget, dates and progress of a parent element are therefore derived from the elements below it.
Equivalents in other frameworks
No equivalents have been recorded for this term yet.
Classification
- this term
- Parent element
- Topic area
- Planning and project structure
Distinction
The child element is the counterpart; one and the same element can be a child in relation to the level above and a parent in relation to the level below. A work package at the lowest level is never a parent element. In a schedule, a summary activity plays a similar role for activities.
In practice
In the work breakdown structure for an office move, "IT move" is a parent element with the child elements "Network at new site", "Server move" and "Set up workstations". A team member wants to book effort for coordination with the landlord directly to the IT move. Instead, the project manager creates a fourth child element, so that the work remains visible and the totals still add up.
Frequently asked questions
Why does a parent element have no work of its own?
Because that work would otherwise not appear in any work package and could get lost in planning, budgeting and progress measurement. The 100 % rule requires all work to be represented in the child elements.
How many child elements should it have?
At least two, otherwise the breakdown is pointless. More than about ten often indicates that an intermediate level is missing.
Source and context
- Reference
- ISO 21506:2024, 3.43
- Edition
- ISO 21506:2024
- Author
- Dennis Hain
Cite this entry
Hain, D. (n.d.). Parent element. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/parent-element/
Hain, D. (n.d.): Parent element. PMDecoder, entry on ISO 21506:2024, 3.43. https://pmdecoder.com/en/glossary/parent-element/ (retrieved 24 November 2026)
@misc{parentelement,
author = {Hain, Dennis},
title = {Parent element},
note = {PMDecoder, ISO 21506:2024, 3.43},
url = {https://pmdecoder.com/en/glossary/parent-element/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/parent-element/"> <p>Element of a work breakdown structure whose work has been split into at least two elements on the level below.</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/parent-element/">Parent element</a>, PMDecoder, ISO 21506:2024, 3.43</footer> </blockquote>
Found a mistake? Let us know, we check every report.