Historical data

Definition

Historical data are documented actual values and experience from earlier projects: actual durations and effort, costs, defect counts, risks that occurred, change rates or productivity figures. Properly prepared, they form the basis for robust estimates, because they show how long comparable work actually took, not just how long it was supposed to take.

Equivalents in other frameworks

No equivalents have been recorded for this term yet.

Classification

this term
Historical data

Distinction

Historical data are figures and facts; lessons learned are the conclusions and recommendations drawn from them. Analogous and parametric estimating methods draw on historical data. Industry benchmarks from studies or databases supplement an organization's own figures, but often fit its own circumstances less closely.

In practice

An engineering consultancy analyses the time records of its last forty bridge inspections. This shows that report writing takes on average twice as long as calculated, while the on-site inspection is mostly on plan. The consultancy adjusts its costing template and in the following year has significantly fewer contracts that fail to cover their costs. The prerequisite was that hours had been recorded against the same activities for years.

Frequently asked questions

Why is historical data so often missing?

Because actual values are not recorded, or are recorded in changing structures, and projects are not evaluated after closure.

How does historical data become usable?

Through uniform recording structures, a brief post-calculation at the end of the project and a central, searchable repository.

Source and context

Cite this entry
APA

Hain, D. (n.d.). Historical data. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/historical-data/

Short form

Hain, D. (n.d.): Historical data. PMDecoder. https://pmdecoder.com/en/glossary/historical-data/ (retrieved 24 November 2026)

BibTeX
@misc{historicaldata,
  author  = {Hain, Dennis},
  title   = {Historical data},
  note    = {PMDecoder},
  url     = {https://pmdecoder.com/en/glossary/historical-data/},
  urldate = {2026-11-24}
}

Embed this definition

HTML fragment for your own website: short definition with source and link, no script and no tracking.

HTML
<blockquote cite="https://pmdecoder.com/en/glossary/historical-data/">
  <p>Recorded information from completed projects used for estimating, planning and risk assessment in new undertakings</p>
  <footer>Source: <a href="https://pmdecoder.com/en/glossary/historical-data/">Historical data</a>, PMDecoder</footer>
</blockquote>

Found a mistake? Let us know, we check every report.