Basis of estimate
abbr. BOE
Definition
The basis of estimate records how an estimate was arrived at. It names the data used, such as experience from earlier projects, quotations or benchmarks, the method applied, the assumptions made, known exclusions and the expected accuracy. This means that the quantities of staff, materials, equipment and money allowed for the activities can still be checked, compared and adjusted in a targeted way later on.
Equivalents in other frameworks
No equivalents have been recorded for this term yet.
Classification
- this term
- Basis of estimate
- Topic area
- Resources and estimating
Distinction
The estimate is the figure, the basis of estimate the justification behind it. Planning assumptions are part of it but not the whole. A commercial costing applies prices and surcharges; the basis of estimate may refer to it, but mainly explains how quantities and effort were derived.
In practice
An engineering firm estimates 4,200 hours for designing a bridge. The basis of estimate states that the figure was derived from three comparable bridges and increased by 15 per cent because of more difficult foundations, that the permit design assumes the legal situation at the time and that environmental reports are not included. When the client disputes additional hours two years later, this document makes it possible to show which assumptions have changed.
Frequently asked questions
What belongs in a basis of estimate?
At least the subject of the estimate, data sources, method, assumptions, exclusions, risks, the expected range, and the date and name of the person who prepared the estimate.
Why is the effort worthwhile?
Because estimates without a justification can neither be checked nor sensibly adjusted. If an assumption changes, the basis of estimate immediately shows which figures are affected.
Source and context
- Reference
- ISO 21506:2024, 3.5
- Edition
- ISO 21506:2024
- Author
- Dennis Hain
Cite this entry
Hain, D. (n.d.). Basis of estimate. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/basis-of-estimate/
Hain, D. (n.d.): Basis of estimate. PMDecoder, entry on ISO 21506:2024, 3.5. https://pmdecoder.com/en/glossary/basis-of-estimate/ (retrieved 24 November 2026)
@misc{basisofestimate,
author = {Hain, Dennis},
title = {Basis of estimate},
note = {PMDecoder, ISO 21506:2024, 3.5},
url = {https://pmdecoder.com/en/glossary/basis-of-estimate/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/basis-of-estimate/"> <p>Record of the data, assumptions and methods on which an estimate of what the planned activities will need is based.</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/basis-of-estimate/">Basis of estimate</a>, PMDecoder, ISO 21506:2024, 3.5</footer> </blockquote>
Found a mistake? Let us know, we check every report.