Basis of estimate

abbr. BOE

Definition

The basis of estimate records how an estimate was arrived at. It names the data used, such as experience from earlier projects, quotations or benchmarks, the method applied, the assumptions made, known exclusions and the expected accuracy. This means that the quantities of staff, materials, equipment and money allowed for the activities can still be checked, compared and adjusted in a targeted way later on.

Equivalents in other frameworks

No equivalents have been recorded for this term yet.

Classification

this term
Basis of estimate

Distinction

The estimate is the figure, the basis of estimate the justification behind it. Planning assumptions are part of it but not the whole. A commercial costing applies prices and surcharges; the basis of estimate may refer to it, but mainly explains how quantities and effort were derived.

In practice

An engineering firm estimates 4,200 hours for designing a bridge. The basis of estimate states that the figure was derived from three comparable bridges and increased by 15 per cent because of more difficult foundations, that the permit design assumes the legal situation at the time and that environmental reports are not included. When the client disputes additional hours two years later, this document makes it possible to show which assumptions have changed.

Frequently asked questions

What belongs in a basis of estimate?

At least the subject of the estimate, data sources, method, assumptions, exclusions, risks, the expected range, and the date and name of the person who prepared the estimate.

Why is the effort worthwhile?

Because estimates without a justification can neither be checked nor sensibly adjusted. If an assumption changes, the basis of estimate immediately shows which figures are affected.

Source and context

Reference
ISO 21506:2024, 3.5
Edition
ISO 21506:2024
Cite this entry
APA

Hain, D. (n.d.). Basis of estimate. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/basis-of-estimate/

Short form

Hain, D. (n.d.): Basis of estimate. PMDecoder, entry on ISO 21506:2024, 3.5. https://pmdecoder.com/en/glossary/basis-of-estimate/ (retrieved 24 November 2026)

BibTeX
@misc{basisofestimate,
  author  = {Hain, Dennis},
  title   = {Basis of estimate},
  note    = {PMDecoder, ISO 21506:2024, 3.5},
  url     = {https://pmdecoder.com/en/glossary/basis-of-estimate/},
  urldate = {2026-11-24}
}

Embed this definition

HTML fragment for your own website: short definition with source and link, no script and no tracking.

HTML
<blockquote cite="https://pmdecoder.com/en/glossary/basis-of-estimate/">
  <p>Record of the data, assumptions and methods on which an estimate of what the planned activities will need is based.</p>
  <footer>Source: <a href="https://pmdecoder.com/en/glossary/basis-of-estimate/">Basis of estimate</a>, PMDecoder, ISO 21506:2024, 3.5</footer>
</blockquote>

Found a mistake? Let us know, we check every report.