Resource histogram

also: Resource loading chart

Definition

A resource histogram plots, for a resource or group of resources over time, how much capacity is planned in each week, day or month. A horizontal line marks the available capacity. Columns above this line show overloads, deep troughs show unused capacity. The chart is an important aid for resource levelling.

Equivalents in other frameworks

No equivalents have been recorded for this term yet.

Classification

this term
Resource histogram

Distinction

The S-curve shows cumulative values over time, the histogram the demand per time period. A utilization table contains the same information as figures but is less clear at a glance. The organization chart shows who holds which role; the histogram shows how heavily those involved are loaded.

In practice

A construction company plans its crane operators for the next six months. The resource histogram shows a column of seven crane operators needed in March, while five are available; in May, by contrast, only three are deployed. The planners check which sites could postpone their crane work in March by a few weeks and find two building projects with sufficient float.

Frequently asked questions

For which resources is a histogram worthwhile?

For scarce and expensive resources where overload or idle time has noticeable consequences, such as specialists, large equipment or test rigs.

Which time scale should be chosen?

That depends on the level of planning detail. Weeks are common for staff; for large equipment on construction sites, days are often used.

Source and context

Cite this entry
APA

Hain, D. (n.d.). Resource histogram. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/resource-histogram/

Short form

Hain, D. (n.d.): Resource histogram. PMDecoder. https://pmdecoder.com/en/glossary/resource-histogram/ (retrieved 24 November 2026)

BibTeX
@misc{resourcehistogram,
  author  = {Hain, Dennis},
  title   = {Resource histogram},
  note    = {PMDecoder},
  url     = {https://pmdecoder.com/en/glossary/resource-histogram/},
  urldate = {2026-11-24}
}

Embed this definition

HTML fragment for your own website: short definition with source and link, no script and no tracking.

HTML
<blockquote cite="https://pmdecoder.com/en/glossary/resource-histogram/">
  <p>Column chart showing the planned demand for a resource per time period, often compared with the available capacity</p>
  <footer>Source: <a href="https://pmdecoder.com/en/glossary/resource-histogram/">Resource histogram</a>, PMDecoder</footer>
</blockquote>

Found a mistake? Let us know, we check every report.