Resource

Definition

Resources are all the means a project uses to produce its results. A distinction is made between consumable resources such as materials or budget, which are used up as they are used, and non-consumable resources such as staff, machines or rooms, which have a limited capacity per unit of time. Resources are planned, assigned to activities and monitored for utilization.

Equivalents in other frameworks

No equivalents have been recorded for this term yet.

Classification

this term
Resource

Distinction

Einsatzmittel is the term used in German standards and means the same thing. In everyday language, resource is often used only for staff, but the technical meaning is broader. Capacity states how much a resource can deliver in a given period; utilization states how much of that capacity has already been planned.

In practice

An exhibition stand builder plans three kinds of resources for the spring season: fitters, vans and a CNC milling machine. The fitters are the bottleneck because four trade fairs take place in the same week, whereas the milling machine is only half utilized. The planners therefore move prefabrication to quieter weeks, so that at the fairs the fitters only have to assemble and no longer have to cut parts to size.

Frequently asked questions

Are people resources?

In planning terms, yes, because their working time is limited and has to be planned. Many organizations nevertheless deliberately speak of staff or employees to underline the difference from machines.

What is a bottleneck resource?

A resource whose limited capacity determines the progress of several activities or projects. It deserves particular attention in planning.

Source and context

Cite this entry
APA

Hain, D. (n.d.). Resource. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/resource/

Short form

Hain, D. (n.d.): Resource. PMDecoder. https://pmdecoder.com/en/glossary/resource/ (retrieved 24 November 2026)

BibTeX
@misc{resource,
  author  = {Hain, Dennis},
  title   = {Resource},
  note    = {PMDecoder},
  url     = {https://pmdecoder.com/en/glossary/resource/},
  urldate = {2026-11-24}
}

Embed this definition

HTML fragment for your own website: short definition with source and link, no script and no tracking.

HTML
<blockquote cite="https://pmdecoder.com/en/glossary/resource/">
  <p>Staff, equipment, materials, facilities or funds that a project needs to carry out its work and that are planned for it</p>
  <footer>Source: <a href="https://pmdecoder.com/en/glossary/resource/">Resource</a>, PMDecoder</footer>
</blockquote>

Found a mistake? Let us know, we check every report.