Brooks's law
Definition
Brooks's law goes back to Frederick P. Brooks, who formulated it in 1975 in his book on experiences from large software projects. New team members need onboarding, which ties up experienced staff, and with every additional person the number of communication relationships grows disproportionately. In addition, many tasks cannot be divided up at will. In the short term, output therefore falls before it rises.
Equivalents in other frameworks
No equivalents have been recorded for this term yet.
Classification
- this term
- Brooks's law
- Topic area
- Resources and estimating
Distinction
The law is a rule of thumb, not a law of nature: early in a project or for clearly delimited tasks, additional staff can indeed speed things up. Crashing deliberately deploys additional resources and must take these limits into account. The statement is often quoted in abbreviated form as an argument against any increase in team size, which goes beyond its original subject.
In practice
A software project is six weeks behind plan, and senior management wants to double the team from six to twelve developers. The project manager does the maths: each newcomer needs three weeks of onboarding by the core team, and the number of communication paths rises from fifteen to sixty-six. Instead, two external testers are brought in for clearly delimited tasks, and the scope of the first version is reduced.
Frequently asked questions
Does the law apply only to software?
It was formulated for software, but the principle applies wherever work requires onboarding and a great deal of coordination.
How many communication paths arise in a team?
With n people, up to n times n minus one, divided by two. Six people with fifteen paths become twelve people with sixty-six.
Source and context
- Author
- Dennis Hain
Cite this entry
Hain, D. (n.d.). Brooks's law. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/brooks-law/
Hain, D. (n.d.): Brooks's law. PMDecoder. https://pmdecoder.com/en/glossary/brooks-law/ (retrieved 24 November 2026)
@misc{brookslaw,
author = {Hain, Dennis},
title = {Brooks's law},
note = {PMDecoder},
url = {https://pmdecoder.com/en/glossary/brooks-law/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/brooks-law/"> <p>Rule of thumb stating that adding staff to a software project that is already late delays it further</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/brooks-law/">Brooks's law</a>, PMDecoder</footer> </blockquote>
Found a mistake? Let us know, we check every report.