Actual date

Definition

Actual dates record when work really began and ended. They are captured as at the status date and replace the previously planned dates of the activities concerned in the schedule. Comparing them with planned and baseline dates reveals schedule variances, and the dates of subsequent activities are recalculated on the basis of the actual dates.

Equivalents in other frameworks

No equivalents have been recorded for this term yet.

Other terms

Other words for the same thing in English usage. Not to be confused with the equivalents above, which translate between frameworks.

Actual start date
related, not equivalent
Actual finish date
related, not equivalent

Classification

this term
Actual date
Topic area
Scheduling

Distinction

The planned date is the current intention, the baseline date the originally approved target, the actual date the fact. A forecast date estimates when an activity that has started or is still outstanding will finish. An actual date is not changed afterwards, except to correct a recording error.

In practice

The installation of a photovoltaic system on a school roof was due to start on 3 June. Because of rain, the installers only start on 6 June, but they finish on 18 June instead of 20 June because an additional colleague joins them. The site manager enters both actual dates. The planning tool recalculates the follow-on work and shows that acceptance by the grid operator can take place two days earlier.

Frequently asked questions

Who reports actual dates?

The people responsible for the activities or work packages, ideally promptly and as at a common status date.

Why are actual dates important?

Because they form the basis for realistic forecasts and, as historical data, help future projects with estimating.

Source and context

Cite this entry
APA

Hain, D. (n.d.). Actual date. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/actual-date/

Short form

Hain, D. (n.d.): Actual date. PMDecoder. https://pmdecoder.com/en/glossary/actual-date/ (retrieved 24 November 2026)

BibTeX
@misc{actualdate,
  author  = {Hain, Dennis},
  title   = {Actual date},
  note    = {PMDecoder},
  url     = {https://pmdecoder.com/en/glossary/actual-date/},
  urldate = {2026-11-24}
}

Embed this definition

HTML fragment for your own website: short definition with source and link, no script and no tracking.

HTML
<blockquote cite="https://pmdecoder.com/en/glossary/actual-date/">
  <p>The point in time at which an activity actually started or finished, as distinct from the planned date</p>
  <footer>Source: <a href="https://pmdecoder.com/en/glossary/actual-date/">Actual date</a>, PMDecoder</footer>
</blockquote>

Found a mistake? Let us know, we check every report.