Imposed date

also: Date constraint

Definition

An imposed date restricts the free calculation of the schedule. It can be set as a fixed date on which an activity must start or finish, or as a limit such as “start no earlier than” or “finish no later than”. Planning tools take such constraints into account in their calculations, so that it becomes visible whether the rest of the plan is compatible with them.

Equivalents in other frameworks

No equivalents have been recorded for this term yet.

Classification

this term
Imposed date
Topic area
Scheduling

Distinction

A calculated date results from durations and dependencies; an imposed date is set independently of them. A milestone can carry an imposed date, but does not have to. Setting too many imposed dates effectively switches off the schedule calculation: the plan then no longer shows conflicts, only wishful dates.

In practice

A grant-funded project must submit its proof of use of funds by 30 June, and according to the grant notice the machines may not be ordered before approval. The project manager enters both as imposed dates: a latest finish date for the proof and an earliest start date for the order. The calculation shows that ten days are missing. The team shortens commissioning rather than jeopardize the deadline.

Frequently asked questions

What kinds of imposed dates are there?

Fixed dates, earliest possible start or finish dates, and latest possible start or finish dates. The names differ from one planning tool to another.

What does negative float mean?

That an imposed date cannot be met with the planned durations and dependencies. Without countermeasures, it will be missed.

Source and context

Cite this entry
APA

Hain, D. (n.d.). Imposed date. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/imposed-date/

Short form

Hain, D. (n.d.): Imposed date. PMDecoder. https://pmdecoder.com/en/glossary/imposed-date/ (retrieved 24 November 2026)

BibTeX
@misc{imposeddate,
  author  = {Hain, Dennis},
  title   = {Imposed date},
  note    = {PMDecoder},
  url     = {https://pmdecoder.com/en/glossary/imposed-date/},
  urldate = {2026-11-24}
}

Embed this definition

HTML fragment for your own website: short definition with source and link, no script and no tracking.

HTML
<blockquote cite="https://pmdecoder.com/en/glossary/imposed-date/">
  <p>Date set from outside that an activity or milestone must meet, for example from a contract, grant funding or an authority's deadline</p>
  <footer>Source: <a href="https://pmdecoder.com/en/glossary/imposed-date/">Imposed date</a>, PMDecoder</footer>
</blockquote>

Found a mistake? Let us know, we check every report.