Project management plan or Project Plan?

false friend · no overlap

Despite its name, the PRINCE2 Project Plan is not the comprehensive project management plan. It is only one part of the Project Initiation Documentation.

Comparison of Project management plan and Project Plan
PMI / PMBOK GuideProject management planPRINCE2Project Plan
What it coversCentral planning document of a project that bundles subsidiary plans and baselines and lays down how the project is run, steered and brought to a close.PRINCE2 plan showing for the whole project which major products are delivered when, with which resources and at what cost.
Equivalent in ISO 21506Project management plan equivalentProject management plan false friend
To the term pageProject management planProject Plan