Project management plan or Project plan?
false friend · no overlap
In everyday usage, “project plan” rarely means the full plan, despite the same name. It usually refers only to the schedule, not to all subsidiary plans.
| PMI / PMBOK GuideProject management plan | cross-frameworkProject plan | |
|---|---|---|
| What it covers | Central planning document of a project that bundles subsidiary plans and baselines and lays down how the project is run, steered and brought to a close. | In everyday usage usually the schedule; in the PMBOK Guide, by contrast, a far more comprehensive document. |
| Equivalent in ISO 21506 | Project management plan equivalent | Project plan false friend |