Kanban glossary
Kanban is a method for making the flow of work visible, limiting work in progress and improving the workflow step by step on the basis of measured flow data.
Independent presentation. The original text is authoritative in each case.
Term hierarchy
- FlowAbschnitt Why Use Kanban
- Kanban systemAbschnitt Definition of KanbanKanban-System
- Flow metricsAbschnitt Flow MetricsFlow-Metriken
- Kanban practicesAbschnitt Kanban PracticesKanban-Praktiken
- Kanban system memberAbschnitt Definition of KanbanKanban-System-Mitglied
Frequently asked questions
Is there a binding definition of Kanban?
There are two widely used guides. The Kanban Guide, currently in its May 2025 version and openly licensed, describes a deliberately minimal set of rules around the Definition of Workflow. Kanban University describes the Kanban Method according to David J. Anderson with principles and general practices. Both share the core: make work visible, limit it and improve the flow.
Which metrics does the Kanban Guide require?
The Kanban Guide names four flow metrics as a minimum: the amount of work started but not finished (WIP), throughput per unit of time, the age of work items in progress (Work Item Age) and the time from start to finish of a work item (Cycle Time). Teams are free to use other names for these measures.
What is a WIP limit?
A WIP limit caps how many work items may be in a part of the workflow at the same time. New work is only pulled in when capacity becomes free. This shortens waiting times, exposes bottlenecks and helps to finish work that has been started before new work begins.
How does Kanban differ from Scrum?
Scrum works in Sprints of fixed length with defined accountabilities and events. Kanban prescribes neither iterations nor roles; it starts from the existing workflow and improves it step by step by limiting work in progress and using flow metrics. Many teams combine both approaches.
Where does the term Kanban come from?
Kanban is Japanese and roughly means card or signal. In manufacturing, best known from the Toyota Production System, kanban cards control the replenishment of material according to the pull principle. The Kanban Method for knowledge work transfers this idea to tasks and services.