Flow metrics
Definition
Flow metrics are the measures that the Kanban Guide requires as a minimum to track the health and performance of a Kanban system. There are four: Work in Progress as the count of items that have been started and not yet finished, Throughput as the count of items completed in a given period, Work Item Age as the time elapsed so far for items in progress, and Cycle Time as the duration of completed items from start to finish. Start and finish are determined by the Definition of Workflow. The figures mean nothing on their own; they are intended to support the three Kanban practices. Teams may name the metrics differently and add further measures.
Equivalents in other frameworks
No equivalents have been recorded for this term yet.
Classification
- Broader term
- Kanban system
- this term
- Flow metrics
- Narrower terms
- Cycle TimeThroughputWork in ProgressWork Item Age
Distinction
Traditional project measures such as cost variance or percent complete measure status against a plan. Flow metrics, by contrast, describe how work actually flows through a system and serve as a basis for forecasts. Velocity in story points measures estimated size; throughput counts finished items.
In practice
A customer service team at a bank looks at its flow metrics in a chart every Monday. Last week 140 requests were closed, 35 are open, and the average cycle time was three days. Four requests stand out whose Work Item Age exceeds two weeks. The team looks at these first and finds that they all involve a query to the lending department.
Frequently asked questions
Why these four measures in particular?
Together they show how much work is in the system, how much gets finished, how long work in progress has already taken and how long completed work took. Bottlenecks and forecasts can be derived from this.
Do the metrics have to be shown in charts?
The 2025 Kanban Guide leaves this to the members. Charts are common, such as cycle time scatterplots or cumulative flow diagrams.
Source and context
- Reference
- Kanban Guide 2025.5, Abschnitt Flow Metrics
- Edition
- The Kanban Guide, May 2025
Differences from other editions
- The Kanban Guide, December 2020
- The section was called Kanban Measures and referred to flow measures or metrics. The guide explicitly recommended presenting the measurements in charts but left the type of chart open.
Cite this entry
Flow metrics. (n.d.). In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/flow-metrics/
Flow metrics (n.d.). PMDecoder, entry on Kanban Guide 2025.5, Abschnitt Flow Metrics. https://pmdecoder.com/en/glossary/flow-metrics/ (retrieved 24 November 2026)
@misc{flowmetrics,
title = {Flow metrics},
note = {PMDecoder, Kanban Guide 2025.5, Abschnitt Flow Metrics},
url = {https://pmdecoder.com/en/glossary/flow-metrics/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/flow-metrics/"> <p>The four mandatory measures of the Kanban Guide: Work in Progress, Throughput, Work Item Age and Cycle Time</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/flow-metrics/">Flow metrics</a>, PMDecoder, Kanban Guide 2025.5, Abschnitt Flow Metrics</footer> </blockquote>
Found a mistake? Let us know, we check every report.