Blocked work
also: Blocked items
Definition
Blocked work refers to work items that have been started but cannot be worked on further because of an impediment, for example because a delivery is missing, a decision is pending or a technical problem is unsolved. The Kanban Guide names resolving such blockers as one form of actively managing work in the workflow. Blocked items still count as work in progress, so they occupy slots within the limit, and their Work Item Age keeps growing. Teams therefore usually make blockers visible on the board, address them first and later analyse which causes occur frequently in order to improve the workflow.
Equivalents in other frameworks
No equivalents have been recorded for this term yet.
Classification
- Broader term
- Kanban practices
- this term
- Blocked work
Distinction
Waiting is not always a blocker: an item in a planned waiting state, such as "awaiting approval", is following the workflow. It is blocked when it is stuck unexpectedly. In Scrum, such obstacles are called impediments, and ensuring that they are removed is one of the Scrum Master's tasks.
In practice
On the board of a team that produces training materials, an item gets a red sticker with the date as soon as it is stuck. In the morning meeting, the team starts with these items. After a quarter, it counts the stickers: more than half of the blockers arose because subject matter experts did not give feedback in time. The team then agrees fixed consultation hours with the specialist departments.
Frequently asked questions
Should blocked items be excluded from the limit?
The Kanban Guide mentions no such exception. Anyone who keeps counting them feels the cost of the blocker and has an incentive to resolve it quickly. Exceptions would have to be explicitly agreed.
Who resolves blockers?
The members of the Kanban system together. If the cause lies outside the system, they often have to involve stakeholders or managers.
Source and context
- Reference
- Kanban Guide 2025.5, Abschnitt Actively Managing Items in a Workflow
- Edition
- The Kanban Guide, May 2025
Cite this entry
Blocked work. (n.d.). In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/blocked-work/
Blocked work (n.d.). PMDecoder, entry on Kanban Guide 2025.5, Abschnitt Actively Managing Items in a Workflow. https://pmdecoder.com/en/glossary/blocked-work/ (retrieved 24 November 2026)
@misc{blockedwork,
title = {Blocked work},
note = {PMDecoder, Kanban Guide 2025.5, Abschnitt Actively Managing Items in a Workflow},
url = {https://pmdecoder.com/en/glossary/blocked-work/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/blocked-work/"> <p>Work items that cannot progress in the workflow because an impediment prevents work on them; resolving them is part of active management in Kanban</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/blocked-work/">Blocked work</a>, PMDecoder, Kanban Guide 2025.5, Abschnitt Actively Managing Items in a Workflow</footer> </blockquote>
Found a mistake? Let us know, we check every report.