Transition Plan

Definition

In PM², the Transition Plan describes objectives, prerequisites, activities and responsibilities for the move from the state before the project to the state after it. It is intended to keep interruptions to operations during the changeover to a minimum and to ensure that the results can be used on time, smoothly and without major problems. A successful transition is regarded as an important precondition for the planned benefits to materialize. The Project Manager prepares the plan with input from the core team; the Project Work Plan takes up the activities, which are controlled like any other project work.

Equivalents in other frameworks

No equivalents have been recorded for this term yet.

Distinction

The Transition Plan covers the technical and organizational changeover, such as data migration, parallel operation and the cutover date. The Business Implementation Plan deals with how the organization, its working processes, its culture and its staff take up the results permanently.

In practice

For a new ticketing system in municipal swimming pools, the Transition Plan provides for the changeover outside the season, one week of parallel operation in the smallest pool, migration of the annual passes on the weekend before and a fallback to the old system until the end of the test week.

Frequently asked questions

Who approves the Transition Plan?

The relevant stakeholders review and approve it; the guide explicitly lists it among the artefacts approved by the Project Owner.

Why is the transition part of the Project Work Plan?

So that changeover tasks do not run alongside the project but are planned and monitored with dates, effort and people responsible.

Source and context

Reference
PM²-Leitfaden 3.1, Abschnitt 6.7
Edition
PM² Guide 3.1
Cite this entry
APA

Transition Plan. (n.d.). In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/transition-plan/

Short form

Transition Plan (n.d.). PMDecoder, entry on PM²-Leitfaden 3.1, Abschnitt 6.7. https://pmdecoder.com/en/glossary/transition-plan/ (retrieved 24 November 2026)

BibTeX
@misc{transitionplan,
  title   = {Transition Plan},
  note    = {PMDecoder, PM²-Leitfaden 3.1, Abschnitt 6.7},
  url     = {https://pmdecoder.com/en/glossary/transition-plan/},
  urldate = {2026-11-24}
}

Embed this definition

HTML fragment for your own website: short definition with source and link, no script and no tracking.

HTML
<blockquote cite="https://pmdecoder.com/en/glossary/transition-plan/">
  <p>PM² plan for moving from the old to the new state, intended to minimize disruption to operations and secure the use of the results</p>
  <footer>Source: <a href="https://pmdecoder.com/en/glossary/transition-plan/">Transition Plan</a>, PMDecoder, PM²-Leitfaden 3.1, Abschnitt 6.7</footer>
</blockquote>

Found a mistake? Let us know, we check every report.