Ready for Executing
abbr. RfE
Definition
Ready for Executing (RfE) is the second Phase Gate in PM². Based on the results of the Planning Phase, the Project Manager checks whether its objectives have been achieved, that is, whether the Project Handbook, the Project Work Plan and the other plans are in place and sound. The Project Manager then asks the Project Steering Committee to authorize execution. If planning has revealed significant deviations from the approved Business Case or Project Charter, the committee must also obtain the approval of the Appropriate Governance Body.
Equivalents in other frameworks
No equivalents have been recorded for this term yet.
Classification
- Broader term
- Phase Gate
- this term
- Ready for Executing
Distinction
Ready for Executing releases implementation; Ready for Planning before it concerned entry into planning, and Ready for Closing after it concerns the move into closing. It is the point at which most funds are committed and is therefore often the most critical gate.
In practice
Planning for a new control system for local public transport shows that costs will be 25 percent above the Business Case. The Project Steering Committee therefore does not authorize execution itself but submits the plans to the transport committee as the responsible governance body, which approves a reduced expansion package.
Frequently asked questions
When does Ready for Executing require additional approval?
When planning deviates substantially from the approved Business Case or Project Charter, for example in costs, scope or dates. The Appropriate Governance Body then takes part in the decision.
What does the Project Manager check before Ready for Executing?
Whether the objectives of the Planning Phase have been achieved and all necessary plans are in place; the phase-exit review checklist serves as a guide.
Source and context
- Reference
- PM²-Leitfaden 3.1, Abschnitt 6.9
- Edition
- PM² Guide 3.1
Cite this entry
Ready for Executing. (n.d.). In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/ready-for-executing/
Ready for Executing (n.d.). PMDecoder, entry on PM²-Leitfaden 3.1, Abschnitt 6.9. https://pmdecoder.com/en/glossary/ready-for-executing/ (retrieved 24 November 2026)
@misc{readyforexecuting,
title = {Ready for Executing},
note = {PMDecoder, PM²-Leitfaden 3.1, Abschnitt 6.9},
url = {https://pmdecoder.com/en/glossary/ready-for-executing/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/ready-for-executing/"> <p>Second PM² Phase Gate at the end of planning, at which the Project Steering Committee authorizes implementation of the plans</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/ready-for-executing/">Ready for Executing</a>, PMDecoder, PM²-Leitfaden 3.1, Abschnitt 6.9</footer> </blockquote>
Found a mistake? Let us know, we check every report.