Ready for Planning

abbr. RfP

Definition

Ready for Planning (RfP) is the first of the three Phase Gates in PM². When initiation is complete, the Project Manager checks whether planning can begin and asks the Project Steering Committee to approve both the Business Case and the Project Charter. The basis for this is the phase-exit review checklist. Should the committee reject the Business Case or the Project Charter, there is no planning; the project goes straight to the Closing Phase so that the insights gained are secured and the documents are archived.

Equivalents in other frameworks

No equivalents have been recorded for this term yet.

Classification

Broader term
Phase Gate
this term
Ready for Planning

Distinction

Ready for Planning decides whether planning takes place at all; Ready for Executing decides whether the finished plan is implemented. Ready for Planning does not replace approval by the Appropriate Governance Body, which may additionally be required depending on the organization.

In practice

A project for a shared customer database of two public authorities does not pass Ready for Planning: the Project Steering Committee considers that data protection has not been assessed adequately in the Business Case. Rather than reworking it, the Project Owner stops the project; the Project Manager records the reasons in the Project-End Report.

Frequently asked questions

Which documents must be available for Ready for Planning?

Above all the Business Case and the Project Charter, together with the completed phase-exit review checklist.

Does a rejected Ready for Planning mean the end of the project?

In PM², yes, at first: the project moves into the Closing Phase. A revised proposal can be submitted again later.

Source and context

Reference
PM²-Leitfaden 3.1, Abschnitt 5.5
Edition
PM² Guide 3.1
Cite this entry
APA

Ready for Planning. (n.d.). In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/ready-for-planning/

Short form

Ready for Planning (n.d.). PMDecoder, entry on PM²-Leitfaden 3.1, Abschnitt 5.5. https://pmdecoder.com/en/glossary/ready-for-planning/ (retrieved 24 November 2026)

BibTeX
@misc{readyforplanning,
  title   = {Ready for Planning},
  note    = {PMDecoder, PM²-Leitfaden 3.1, Abschnitt 5.5},
  url     = {https://pmdecoder.com/en/glossary/ready-for-planning/},
  urldate = {2026-11-24}
}

Embed this definition

HTML fragment for your own website: short definition with source and link, no script and no tracking.

HTML
<blockquote cite="https://pmdecoder.com/en/glossary/ready-for-planning/">
  <p>First PM² Phase Gate at the end of initiation, at which the Business Case and the Project Charter are submitted for approval</p>
  <footer>Source: <a href="https://pmdecoder.com/en/glossary/ready-for-planning/">Ready for Planning</a>, PMDecoder, PM²-Leitfaden 3.1, Abschnitt 5.5</footer>
</blockquote>

Found a mistake? Let us know, we check every report.