Project plan or Project Plan?

false friend · no overlap

Despite its name, the PRINCE2 Project Plan is not the comprehensive project management plan. It is only one part of the Project Initiation Documentation.

Comparison of Project plan and Project Plan
ISO 21506Project planPRINCE2Project Plan
What it coversUnder ISO 21506, the binding document that brings together a project's technical baselines and its management baselines.PRINCE2 plan showing for the whole project which major products are delivered when, with which resources and at what cost.
Equivalent in PMI / PMBOK GuideProject management plan equivalentProject management plan false friend
To the term pageProject planProject Plan