Stage Plan

Definition

In PRINCE2, the stage plan is the plan for one management stage. It is detailed enough for the project manager to control day-to-day work with it: it contains the products of the stage, the activities required, dates, resources and costs, the stage tolerances and the planned controls. Because a stage is only planned in detail shortly before it starts, the stage plan is produced towards the end of the preceding stage; the plan for initiation is already drawn up while the project is being prepared. The project board approves the stage plan when it decides on the next stage.

Equivalents in other frameworks

No equivalents have been recorded for this term yet.

Distinction

The project plan covers the whole project and stays broad; the stage plan details one stage of it. A team plan, by contrast, concerns the work of a single team. The approach reflects the idea of rolling wave planning. A management stage does not necessarily coincide with a project phase, because it is aligned with decision points rather than with technical work steps.

In practice

A museum is planning a major special exhibition. Shortly before the end of the design stage, the project manager produces the stage plan for implementation: loan agreements, exhibition architecture, catalogue and accompanying programme, with weekly planning, responsibilities and a budget of 380,000 euros. The project board approves it together with the report on the stage just completed.

Frequently asked questions

Why is the whole project not planned in detail?

Because details of distant stages are hard to predict. Planning in detail later allows lessons from the earlier stages to be taken into account.

What happens if the stage plan cannot be met?

As long as the stage tolerances suffice, the project manager adjusts things. If they are likely to be exceeded, the project manager reports this to the project board, which can request an exception plan.

Source and context

Reference
PRINCE2 7, Praktik Pläne
Edition
PRINCE2 7
Cite this entry
APA

Hain, D. (n.d.). Stage Plan. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/stage-plan/

Short form

Hain, D. (n.d.): Stage Plan. PMDecoder, entry on PRINCE2 7, Praktik Pläne. https://pmdecoder.com/en/glossary/stage-plan/ (retrieved 24 November 2026)

BibTeX
@misc{stageplan,
  author  = {Hain, Dennis},
  title   = {Stage Plan},
  note    = {PMDecoder, PRINCE2 7, Praktik Pläne},
  url     = {https://pmdecoder.com/en/glossary/stage-plan/},
  urldate = {2026-11-24}
}

Embed this definition

HTML fragment for your own website: short definition with source and link, no script and no tracking.

HTML
<blockquote cite="https://pmdecoder.com/en/glossary/stage-plan/">
  <p>Detailed PRINCE2 plan for a single management stage, used by the project manager to control day-to-day work.</p>
  <footer>Source: <a href="https://pmdecoder.com/en/glossary/stage-plan/">Stage Plan</a>, PMDecoder, PRINCE2 7, Praktik Pläne</footer>
</blockquote>

Found a mistake? Let us know, we check every report.