Exception Plan
Definition
In PRINCE2, an exception plan is produced when it is clear that a plan cannot stay within its tolerances and the higher level asks for a new plan. It replaces the affected plan, usually a stage plan, or the project plan in the case of project-level exceptions, and covers the period from the exception to the end of the original planning period. It has the same structure as the plan it replaces and is based on the option the project board has chosen after reviewing the reported exception. On approval, new targets and tolerances apply. The business case is often updated at the same time.
Equivalents in other frameworks
No equivalents have been recorded for this term yet.
Distinction
A corrective action brings a project back on course within its tolerances; an exception plan becomes necessary when that no longer works. Unlike a contingency or fallback plan, it is not drawn up as a precaution but only after the exception has occurred. Nor is it an additional plan; it takes the place of the previous one.
In practice
During the construction of a new school, it emerges in the third stage that contaminated soil has to be disposed of and the cost tolerance will be exceeded twice over. The project manager reports the exception with three options. The project board opts for a modified foundation and requests an exception plan. Once it is approved, the stage continues with a new budget.
Frequently asked questions
Who approves an exception plan?
The level whose tolerances are affected. If it replaces a stage plan, the project board approves it; if it concerns the project plan and project tolerances, the board may have to refer the decision to the commissioning organization.
Are there exception plans for teams too?
If a team exceeds the tolerances of a work package, the team manager reports this to the project manager, who adjusts within the stage tolerances. An exception plan concerns the levels above.
Source and context
- Reference
- PRINCE2 7, Praktik Pläne
- Edition
- PRINCE2 7
- Author
- Dennis Hain
Cite this entry
Hain, D. (n.d.). Exception Plan. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/exception-plan/
Hain, D. (n.d.): Exception Plan. PMDecoder, entry on PRINCE2 7, Praktik Pläne. https://pmdecoder.com/en/glossary/exception-plan/ (retrieved 24 November 2026)
@misc{exceptionplan,
author = {Hain, Dennis},
title = {Exception Plan},
note = {PMDecoder, PRINCE2 7, Praktik Pläne},
url = {https://pmdecoder.com/en/glossary/exception-plan/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/exception-plan/"> <p>PRINCE2 plan that, at the project board’s request, replaces a plan whose tolerances are forecast to be exceeded.</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/exception-plan/">Exception Plan</a>, PMDecoder, PRINCE2 7, Praktik Pläne</footer> </blockquote>
Found a mistake? Let us know, we check every report.