Project Initiation Documentation or Project plan?
false friend · no overlap
In everyday usage, “project plan” rarely means the full plan, despite the same name. It usually refers only to the schedule, not to all subsidiary plans.
| PRINCE2Project Initiation Documentation | cross-frameworkProject plan | |
|---|---|---|
| What it covers | Set of PRINCE2 management products defining the project; the project board authorizes the project by approving it. | In everyday usage usually the schedule; in the PMBOK Guide, by contrast, a far more comprehensive document. |
| Equivalent in ISO 21506 | Project management plan closely related | Project plan false friend |
| To the term page | Project Initiation Documentation | Project plan |