Focus on products principle
Definition
The focus on products principle requires a PRINCE2 project to establish first what it is to deliver and only then which activities are needed to deliver it. Products are all outputs, tangible or intangible, including the documents used to manage the project. For each significant product the team describes its purpose, its composition and the quality criteria against which it will be judged. These descriptions form the basis for planning, estimating, work allocation, quality checking and acceptance. The principle is meant to prevent stakeholders from holding different ideas about the result and to avoid work that contributes nothing recognizable to it.
Equivalents in other frameworks
No equivalents have been recorded for this term yet.
Distinction
A work breakdown structure often breaks down the work; PRINCE2 starts from the results with a product breakdown structure and derives the work from it. The term product is broader in PRINCE2 than in everyday language and is closer to deliverable. The principle shares only the word with the Scrum Product Owner.
In practice
For the redesign of a museum gallery, the team first defines the products: spatial concept, exhibition texts, media stations, lighting and step-free visitor routes. For the media stations, for instance, it is stated that they must be usable without instructions and available in two languages. Only then are work steps, responsibilities and dates planned.
Frequently asked questions
Are reports and plans also products in PRINCE2?
Yes. PRINCE2 distinguishes management products, which serve to run the project, from specialist products, which are handed over to users.
What does the product view achieve in practice?
It clarifies early what counts as finished. Effort can be estimated more reliably, and disputes at acceptance become rarer because the criteria were agreed beforehand.
Source and context
- Reference
- PRINCE2 7, Grundprinzipien
- Edition
- PRINCE2 7
- Author
- Dennis Hain
Cite this entry
Hain, D. (n.d.). Focus on products principle. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/focus-on-products-principle/
Hain, D. (n.d.): Focus on products principle. PMDecoder, entry on PRINCE2 7, Grundprinzipien. https://pmdecoder.com/en/glossary/focus-on-products-principle/ (retrieved 24 November 2026)
@misc{focusonproductsprinciple,
author = {Hain, Dennis},
title = {Focus on products principle},
note = {PMDecoder, PRINCE2 7, Grundprinzipien},
url = {https://pmdecoder.com/en/glossary/focus-on-products-principle/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/focus-on-products-principle/"> <p>PRINCE2 principle: planning and control are organized around the products to be delivered and their agreed quality requirements.</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/focus-on-products-principle/">Focus on products principle</a>, PMDecoder, PRINCE2 7, Grundprinzipien</footer> </blockquote>
Found a mistake? Let us know, we check every report.