Managing a stage boundary or Phase gate?
partially overlapping
In PRINCE2, Managing a stage boundary relates, like a gate, to the move between stages. It is the process that prepares the Project Board's decision.
| PRINCE2Managing a stage boundary | PMI / PMBOK GuidePhase gate | |
|---|---|---|
| What it covers | PRINCE2 process at the end of a stage: assessing results, planning the next stage, updating the business case and preparing authorization. | Formal decision point between two phases at which an authorized body uses the phase results to decide how the undertaking proceeds. |
| Equivalent in ISO 21506 | Gate partially overlapping | Gate equivalent |
| To the term page | Managing a stage boundary | Phase gate |