Manage by stages
Definition
Under the manage by stages principle, a PRINCE2 project is divided into successive management stages. The Project Board authorizes only one stage at a time and, at the end of each, decides on the basis of the current situation whether and how the project should continue. The idea is that only the near future can be planned reliably in detail: there is a detailed plan for the current stage and a less detailed one for the project as a whole. Each stage therefore provides a control point at which the business case, risks and plans are reviewed. Every project has at least two stages: the initiation stage and at least one further stage.
Equivalents in other frameworks
No equivalents have been recorded for this term yet.
Distinction
Phase models with gates, as described by ISO 21506 or PMI, follow a similar idea. In PRINCE2, however, management stages are explicitly units of direction and authorization; they need not coincide with technical stages such as design, build and test. Iterations in agile approaches are much shorter, and several of them can take place within a single management stage.
In practice
An energy utility is modernizing its control centre. The Project Board first authorizes only initiation, then a stage for tendering and contract award. Only when the bids are in and the costs are reliable does it approve the stage for installation and commissioning. In this way it commits the large budget only once uncertainty has dropped considerably.
Frequently asked questions
How long should a management stage be?
PRINCE2 does not set a fixed length. What matters is the level of risk, how far ahead planning is reliable, and the points at which meaningful decisions can be made, such as after a contract award or a pilot.
Does the principle fit agile working?
Yes. Management stages provide the framework for authorization, within which teams can work in short cycles and deliver products incrementally.
Source and context
- Reference
- PRINCE2 7, Grundprinzipien
- Edition
- PRINCE2 7
- Author
- Dennis Hain
Cite this entry
Hain, D. (n.d.). Manage by stages. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/manage-by-stages/
Hain, D. (n.d.): Manage by stages. PMDecoder, entry on PRINCE2 7, Grundprinzipien. https://pmdecoder.com/en/glossary/manage-by-stages/ (retrieved 24 November 2026)
@misc{managebystages,
author = {Hain, Dennis},
title = {Manage by stages},
note = {PMDecoder, PRINCE2 7, Grundprinzipien},
url = {https://pmdecoder.com/en/glossary/manage-by-stages/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/manage-by-stages/"> <p>PRINCE2 principle: the project is planned, monitored and authorized in management stages, each ending with a decision.</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/manage-by-stages/">Manage by stages</a>, PMDecoder, PRINCE2 7, Grundprinzipien</footer> </blockquote>
Found a mistake? Let us know, we check every report.