Exception Report
Definition
In PRINCE2 the Exception Report is the report through which the Project Manager informs the Project Board of an exception: a forecast shows that the current stage or the project will exceed one of the agreed tolerances, for example for time, cost or scope. Because the Project Manager may only decide within these tolerances, the situation must be passed to the next level up. The report describes the cause and consequences of the deviation, sets out the options with their effects on the business case, risks and tolerances, and makes a recommendation. The Board then decides, for example on a new plan for the rest of the stage, an adjustment of tolerances or premature closure. The report puts the principle of management by exception into practice.
Equivalents in other frameworks
No equivalents have been recorded for this term yet.
Distinction
The Highlight Report reports normal progress within tolerances; the Exception Report reports a foreseeable breach and calls for a decision. A variance threshold in ISO 21506 serves a similar purpose but is a value, not a report. An Issue Report deals with a single issue; if that issue leads to a tolerance breach, an Exception Report follows as well.
In practice
In a project to build a sports hall, it emerges during the shell construction stage that contaminated soil must be replaced. The Project Manager expects additional costs well beyond the stage cost tolerance. He prepares an Exception Report with three options: absorb the extra cost, reduce the fittings or build a smaller hall. He recommends the first option and asks the Board to request a plan for the rest of the stage.
Frequently asked questions
When must an Exception Report be produced?
As soon as a forecast shows that a stage or the project will exceed an agreed tolerance. It should be available before the breach occurs so that the Board can still act.
What follows an Exception Report?
The Project Board decides on the recommendation. It often asks for a plan to replace the current stage or project plan, but it can also adjust tolerances or close the project.
Source and context
- Reference
- PRINCE2 7, Praktik Fortschritt
- Edition
- PRINCE2 7
- Author
- Dennis Hain
Cite this entry
Hain, D. (n.d.). Exception Report. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/exception-report/
Hain, D. (n.d.): Exception Report. PMDecoder, entry on PRINCE2 7, Praktik Fortschritt. https://pmdecoder.com/en/glossary/exception-report/ (retrieved 24 November 2026)
@misc{exceptionreport,
author = {Hain, Dennis},
title = {Exception Report},
note = {PMDecoder, PRINCE2 7, Praktik Fortschritt},
url = {https://pmdecoder.com/en/glossary/exception-report/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/exception-report/"> <p>PRINCE2 report from the Project Manager to the Project Board when a stage or the project is forecast to exceed its agreed tolerances.</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/exception-report/">Exception Report</a>, PMDecoder, PRINCE2 7, Praktik Fortschritt</footer> </blockquote>
Found a mistake? Let us know, we check every report.