Manage by exception principle
Definition
The manage by exception principle governs how authority is distributed between the levels of a PRINCE2 project. Each level sets objectives and tolerances for the level below, that is, permitted margins for aspects such as time, cost, scope or quality. As long as the forecast stays within those limits, the lower level works independently and reports at agreed intervals. If a tolerance is forecast to be exceeded, an exception exists and is escalated to the next level up. This relieves senior management, which only needs to deal with matters that genuinely require its decision.
Equivalents in other frameworks
No equivalents have been recorded for this term yet.
Distinction
Management by exception in general business administration describes the same basic idea. PRINCE2 makes it binding and links it to defined tolerances, reports and levels. Deviations within tolerance are not yet an exception; the responsible level resolves them itself, for example through corrective action.
In practice
For one stage of a software project, the Project Board approves 400,000 euros with a tolerance of ten per cent and an end date with two weeks of leeway. The project manager absorbs a one-week delay by replanning. When a supplier drops out and costs threaten to rise by 15 per cent, he informs the Project Board immediately and presents options.
Frequently asked questions
Does this mean the Project Board only hears about problems?
No. It receives regular progress reports and stays informed. It only has to make decisions when a tolerance is at risk or an authorization is due.
Who sets the tolerances?
The level above in each case: the commissioning organization for the project, the Project Board for the stages, and the project manager for work packages.
Source and context
- Reference
- PRINCE2 7, Grundprinzipien
- Edition
- PRINCE2 7
- Author
- Dennis Hain
Cite this entry
Hain, D. (n.d.). Manage by exception principle. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/manage-by-exception-principle/
Hain, D. (n.d.): Manage by exception principle. PMDecoder, entry on PRINCE2 7, Grundprinzipien. https://pmdecoder.com/en/glossary/manage-by-exception-principle/ (retrieved 24 November 2026)
@misc{managebyexceptionprinciple,
author = {Hain, Dennis},
title = {Manage by exception principle},
note = {PMDecoder, PRINCE2 7, Grundprinzipien},
url = {https://pmdecoder.com/en/glossary/manage-by-exception-principle/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/manage-by-exception-principle/"> <p>PRINCE2 principle: authority is delegated with tolerances; the higher level steps in only when a tolerance is forecast to be exceeded.</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/manage-by-exception-principle/">Manage by exception principle</a>, PMDecoder, PRINCE2 7, Grundprinzipien</footer> </blockquote>
Found a mistake? Let us know, we check every report.