Appropriate Governance Body
abbr. AGB
Definition
In PM², the Appropriate Governance Body (AGB) is the body that decides on an organization's strategic planning and portfolio. For an individual project, it is the authority that agrees to the undertaking and its objective and provides the necessary funds. It determines which programmes and projects are carried out, monitors portfolio performance and allocates resources. Its members include representatives of both the requesting and the delivering side. Which body actually takes on this role depends on the organization; the name deliberately stresses that it is whichever body is responsible in each case.
Equivalents in other frameworks
No equivalents have been recorded for this term yet.
Distinction
The Project Steering Committee steers an individual project; the Appropriate Governance Body sits above it and looks at the entire portfolio. If a project has to deviate significantly from the approved Business Case or Project Charter, the Project Steering Committee needs the approval of the governance body. In general usage it corresponds most closely to a portfolio or investment committee.
In practice
In a directorate-general, the IT investment committee decides on new projects twice a year. It reviews the Business Case for an electronic complaints portal, compares it with three competing proposals and releases the budget for the first two phases. When planning shows that costs will rise by a third, the Project Steering Committee refers the matter back to the investment committee.
Frequently asked questions
Does every PM² project have to be approved by the Appropriate Governance Body?
That depends on the size and importance of the project. Smaller projects can also be approved by the Project Owner; larger or strategically important projects go to the responsible body.
Is the body part of the project organization?
It belongs to the organization's Business Governing Layer and therefore not to the project team. The project reports to it via the Project Steering Committee.
Source and context
- Reference
- PM²-Leitfaden 3.1, Abschnitt 4.3
- Edition
- PM² Guide 3.1
Cite this entry
Appropriate Governance Body. (n.d.). In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/appropriate-governance-body/
Appropriate Governance Body (n.d.). PMDecoder, entry on PM²-Leitfaden 3.1, Abschnitt 4.3. https://pmdecoder.com/en/glossary/appropriate-governance-body/ (retrieved 24 November 2026)
@misc{appropriategovernancebody,
title = {Appropriate Governance Body},
note = {PMDecoder, PM²-Leitfaden 3.1, Abschnitt 4.3},
url = {https://pmdecoder.com/en/glossary/appropriate-governance-body/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/appropriate-governance-body/"> <p>Body of the organization that decides on strategy and portfolio in PM², approves projects and releases the funds for them</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/appropriate-governance-body/">Appropriate Governance Body</a>, PMDecoder, PM²-Leitfaden 3.1, Abschnitt 4.3</footer> </blockquote>
Found a mistake? Let us know, we check every report.