Business Manager
abbr. BM
Definition
In PM², the Business Manager (BM) acts on behalf of the Project Owner on a daily basis. The role describes the business objectives in the Project Initiation Request, the Business Case and the Business Implementation Plan, coordinates the Business Implementation Group and the User Representatives, and maintains close and reliable contact with the Project Manager. The Business Manager makes sure that the delivered results meet the users' needs, provides the resources of the business side, prepares the organization for the results and plans training for the users.
Equivalents in other frameworks
No equivalents have been recorded for this term yet.
Distinction
The name Business Manager can easily be misleading: it does not refer to general management but to the customer side of the project. The task overlaps only partly with the classic role of a requirements engineer, because organizational implementation is also part of it. The Project Manager is the counterpart on the provider side.
In practice
When an online appointment booking system is introduced for a citizens' office, the deputy head of the office is the Business Manager. She gathers the requirements with two caseworkers, aligns them weekly with the Project Manager and plans the changes to counter opening hours. She schedules staff training for the week before go-live.
Frequently asked questions
How do the Business Manager and the Project Manager work together?
They coordinate continuously: the Project Manager is responsible for delivery, while the Business Manager ensures that the results meet the business requirements and that the organization can take them up.
Which documents is the Business Manager responsible for?
Above all the Business Case and the Business Implementation Plan; the Business Manager often contributes to the Project Initiation Request on behalf of the Project Owner.
Source and context
- Reference
- PM²-Leitfaden 3.1, Abschnitt 4.7
- Edition
- PM² Guide 3.1
Cite this entry
Business Manager. (n.d.). In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/business-manager/
Business Manager (n.d.). PMDecoder, entry on PM²-Leitfaden 3.1, Abschnitt 4.7. https://pmdecoder.com/en/glossary/business-manager/ (retrieved 24 November 2026)
@misc{businessmanager,
title = {Business Manager},
note = {PMDecoder, PM²-Leitfaden 3.1, Abschnitt 4.7},
url = {https://pmdecoder.com/en/glossary/business-manager/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/business-manager/"> <p>PM² role that represents the Project Owner in day-to-day project work, coordinates the business side and prepares the organization for the change</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/business-manager/">Business Manager</a>, PMDecoder, PM²-Leitfaden 3.1, Abschnitt 4.7</footer> </blockquote>
Found a mistake? Let us know, we check every report.