Sustainability Management Approach
Definition
The sustainability management approach describes how a PRINCE2 project takes environmental, social and economic sustainability into account. PRINCE2 7 treats sustainability as a performance target in its own right alongside time, cost, quality, scope, benefits and risk. The approach specifies which sustainability targets apply to the project and its products, where they come from, for example from organizational requirements or legal obligations, how they are measured and who is responsible. It concerns both the way the project works and the characteristics of the outputs over their useful life. It is created during initiation and becomes part of the project initiation documentation.
Equivalents in other frameworks
No equivalents have been recorded for this term yet.
Distinction
An organization’s sustainability reports look at the company as a whole; the approach applies to a single project. It is not an environmental management system in its own right but builds on existing requirements. Earlier PRINCE2 editions had no corresponding management product.
In practice
A retailer is building a new distribution centre. The sustainability management approach adopts the group target of limiting the energy demand of new buildings and specifies that construction waste is recorded separately and the share of recycled material reported. A tolerance for greenhouse gas emissions is agreed for the construction phase; if it is exceeded, the project board is informed.
Frequently asked questions
Why did PRINCE2 7 add sustainability?
Because many organizations have set their own sustainability targets or are legally obliged to, and projects can contribute substantially to them or work against them.
Does the approach apply only to construction and infrastructure projects?
No. IT or organizational projects also have effects, for example through energy consumption, travel or working conditions. The scope of the approach depends on the project.
Source and context
- Reference
- PRINCE2 7, Managementprodukte
- Edition
- PRINCE2 7
- Author
- Dennis Hain
Cite this entry
Hain, D. (n.d.). Sustainability Management Approach. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/sustainability-management-approach/
Hain, D. (n.d.): Sustainability Management Approach. PMDecoder, entry on PRINCE2 7, Managementprodukte. https://pmdecoder.com/en/glossary/sustainability-management-approach/ (retrieved 24 November 2026)
@misc{sustainabilitymanagementapproach,
author = {Hain, Dennis},
title = {Sustainability Management Approach},
note = {PMDecoder, PRINCE2 7, Managementprodukte},
url = {https://pmdecoder.com/en/glossary/sustainability-management-approach/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/sustainability-management-approach/"> <p>PRINCE2 7 management product defining how the project’s sustainability targets are set, measured and controlled.</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/sustainability-management-approach/">Sustainability Management Approach</a>, PMDecoder, PRINCE2 7, Managementprodukte</footer> </blockquote>
Found a mistake? Let us know, we check every report.