Quality control

abbr. QC

Definition

Quality control compares results with the specified requirements. Samples are taken, measurements, tests and inspections carried out and the results evaluated, often with statistical tools such as control charts. If deviations are found, it initiates corrections, rework or blocking of the affected items and provides data for action on the root cause.

Equivalents in other frameworks

No equivalents have been recorded for this term yet.

Classification

this term
Quality control
Topic area
Quality

Distinction

Quality assurance looks at processes and is meant to prevent defects; quality control looks at products and is meant to find them. Inspection is a tool of quality control, not control itself. In German, the English term quality control is rendered as Qualitätskontrolle as well as Qualitätslenkung.

In practice

During the installation of 1,200 windows in a housing project, site management checks every twentieth window for airtightness, correct fitting and proper functioning of the hardware. After two weeks it becomes apparent that one installation crew has a noticeably higher defect rate. All windows installed by this crew are fully inspected and reworked, and the crew is retrained. Over the following weeks the rate returns to the usual range.

Frequently asked questions

How much should be inspected?

As much as is needed to detect defects with reasonable effort. Critical characteristics are often inspected in full; otherwise samples are sufficient.

What happens to defective results?

They are marked and, depending on the case, reworked, repaired, released as an exception with the client's consent or scrapped.

Source and context

Reference
ISO 21506:2024, 3.71
Edition
ISO 21506:2024
Cite this entry
APA

Hain, D. (n.d.). Quality control. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/quality-control/

Short form

Hain, D. (n.d.): Quality control. PMDecoder, entry on ISO 21506:2024, 3.71. https://pmdecoder.com/en/glossary/quality-control/ (retrieved 24 November 2026)

BibTeX
@misc{qualitycontrol,
  author  = {Hain, Dennis},
  title   = {Quality control},
  note    = {PMDecoder, ISO 21506:2024, 3.71},
  url     = {https://pmdecoder.com/en/glossary/quality-control/},
  urldate = {2026-11-24}
}

Embed this definition

HTML fragment for your own website: short definition with source and link, no script and no tracking.

HTML
<blockquote cite="https://pmdecoder.com/en/glossary/quality-control/">
  <p>Part of quality management that checks work results, identifies deviations from requirements and initiates their correction.</p>
  <footer>Source: <a href="https://pmdecoder.com/en/glossary/quality-control/">Quality control</a>, PMDecoder, ISO 21506:2024, 3.71</footer>
</blockquote>

Found a mistake? Let us know, we check every report.