Risk Management Approach or Risk management plan?

closely related

In PRINCE2, the Risk Management Approach sets out how risks are managed, like a risk management plan. It also turns risk appetite into tolerances.

Comparison of Risk Management Approach and Risk management plan
PRINCE2Risk Management Approachcross-frameworkRisk management plan
What it coversPRINCE2 management product defining how risks in the project are identified, assessed, controlled and reported.Document that defines how risk management is organized and carried out in a project
Equivalent in PMI / PMBOK GuideRisk management plan closely relatedRisk management plan equivalent
To the term pageRisk Management ApproachRisk management plan