Issue Report

Definition

In PRINCE2 the Issue Report is the report on a single issue that is being handled formally and needs closer examination. It can relate to any of the three types: a request for change to an agreed baseline, an off-specification where a product departs from its specification, or any other problem/concern. The report describes the issue, assesses its impact on objectives, business case and risks, sets out options and recommends a solution. Later, the decision, who took it and the date are added. The Issue Report is kept together with the entry in the Issue Register and shows the basis on which the decision was made. Whether a request for change is decided by the Project Manager, a body delegated by the Board or the Project Board itself is set out in the issue management approach.

Equivalents in other frameworks

No equivalents have been recorded for this term yet.

Distinction

The Issue Register lists all formally handled issues in brief; the Issue Report examines one issue in depth. A change request in ISO 21506 or at PMI corresponds to the Issue Report for the request-for-change type, but does not cover off-specifications or general problems. If the impact of an issue exceeds tolerances, the Issue Report is not enough; an Exception Report follows.

In practice

The business department of an online retailer wants to add payment by invoice during the project. After the entry in the Issue Register, the Project Manager prepares an Issue Report: the change costs six person-days, delays go-live by a week and is expected to increase sales. He recommends implementation. The body delegated by the Board to decide on changes agrees; the decision and date are added to the report.

Frequently asked questions

Does every issue need an Issue Report?

No. An Issue Report is only produced for issues that are handled formally and require analysis. Minor matters are dealt with in the Daily Log, and simple entries in the Issue Register do not always need a report of their own.

Is an Issue Report the same as a change request?

Only in part. A request for change is one of the three types of issue in PRINCE2. The Issue Report can equally describe an off-specification or a problem.

Source and context

Reference
PRINCE2 7, Praktik Issues
Edition
PRINCE2 7
Cite this entry
APA

Hain, D. (n.d.). Issue Report. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/issue-report/

Short form

Hain, D. (n.d.): Issue Report. PMDecoder, entry on PRINCE2 7, Praktik Issues. https://pmdecoder.com/en/glossary/issue-report/ (retrieved 24 November 2026)

BibTeX
@misc{issuereport,
  author  = {Hain, Dennis},
  title   = {Issue Report},
  note    = {PMDecoder, PRINCE2 7, Praktik Issues},
  url     = {https://pmdecoder.com/en/glossary/issue-report/},
  urldate = {2026-11-24}
}

Embed this definition

HTML fragment for your own website: short definition with source and link, no script and no tracking.

HTML
<blockquote cite="https://pmdecoder.com/en/glossary/issue-report/">
  <p>PRINCE2 report on a single formally handled issue, with description, impact analysis, recommendation and decision.</p>
  <footer>Source: <a href="https://pmdecoder.com/en/glossary/issue-report/">Issue Report</a>, PMDecoder, PRINCE2 7, Praktik Issues</footer>
</blockquote>

Found a mistake? Let us know, we check every report.