Executing Phase

Definition

As the third stage of the PM² life cycle, the Executing Phase opens with its own kick-off meeting. It is complete once the requestor side has accepted the results, either provisionally or finally, depending on the plan. During this time the Project Core Team produces the deliverables described in the Project Work Plan, and the Project Manager coordinates people and resources, distributes information according to the communication plan and has the agreed quality assurance carried out. In parallel, the requesting organization prepares for the introduction of the results. No other phase typically ties up as many resources or needs as much monitoring.

Equivalents in other frameworks

No equivalents have been recorded for this term yet.

Distinction

The Executing Phase is a period in the project's timeline; the Performing Layer, by contrast, refers to the roles that do the work. In PM², monitoring and controlling is not limited to this phase but runs across the whole project, although it is particularly demanding here.

In practice

In a project for a new HR portal, execution starts with a kick-off for the core team and the Business Implementation Group. The team delivers in three increments; each one is tested according to the Deliverables Acceptance Management Plan and confirmed by the User Representatives. In parallel, the Business Implementation Group trains the managers who will be the first to work with the portal.

Frequently asked questions

When may a PM² project leave the Executing Phase?

When the planned work is done, the requirements are met and the results have been accepted at least provisionally. The Project Steering Committee can then approve the move into the Closing Phase.

Is there still planning in the Executing Phase?

Yes. Plans are adjusted in response to deviations, changes or new risks. The fundamental planning should, however, be complete.

Source and context

Reference
PM²-Leitfaden 3.1, Abschnitte 3.2.3 und 7
Edition
PM² Guide 3.1
Cite this entry
APA

Executing Phase. (n.d.). In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/executing-phase/

Short form

Executing Phase (n.d.). PMDecoder, entry on PM²-Leitfaden 3.1, Abschnitte 3.2.3 und 7. https://pmdecoder.com/en/glossary/executing-phase/ (retrieved 24 November 2026)

BibTeX
@misc{executingphase,
  title   = {Executing Phase},
  note    = {PMDecoder, PM²-Leitfaden 3.1, Abschnitte 3.2.3 und 7},
  url     = {https://pmdecoder.com/en/glossary/executing-phase/},
  urldate = {2026-11-24}
}

Embed this definition

HTML fragment for your own website: short definition with source and link, no script and no tracking.

HTML
<blockquote cite="https://pmdecoder.com/en/glossary/executing-phase/">
  <p>Third PM² phase, in which the team produces the deliverables according to plan and the organization prepares for their introduction</p>
  <footer>Source: <a href="https://pmdecoder.com/en/glossary/executing-phase/">Executing Phase</a>, PMDecoder, PM²-Leitfaden 3.1, Abschnitte 3.2.3 und 7</footer>
</blockquote>

Found a mistake? Let us know, we check every report.