Project Initiation Request
Definition
In PM², a project begins with the Project Initiation Request. It records the situation that gives rise to the project, that is, which problem, need or opportunity exists, and which results are expected. It also contains initial information on effort, costs, time frame and type of delivery, the intended impact, the success criteria, the link to the organization's strategy and the assumptions, constraints and risks that can be identified at this point. Anyone can submit it; depending on the project, it is approved by the Project Owner or by the Appropriate Governance Body. Its content then feeds into the Business Case and the Project Charter.
Equivalents in other frameworks
No equivalents have been recorded for this term yet.
Distinction
The request is deliberately brief and serves only as a basis for further examination. The economic justification comes only with the Business Case, while scope, milestones and deliverables are set out in the Project Charter. In general usage it is most comparable to a project outline.
In practice
A caseworker suggests delivering grant notices electronically in future. The Business Manager turns this into a two-page Project Initiation Request with the objective of saving postage and processing time, a rough cost range and the risk of missing consent from recipients. The head of unit, acting as Project Owner, approves the preparation of a Business Case.
Frequently asked questions
Who may submit a Project Initiation Request?
In principle, anyone in the organization. The Project Owner often delegates its preparation to the Business Manager.
How detailed should the request be?
As short as possible: it should contain the most important information, with the details following in the Business Case and the Project Charter.
Source and context
- Reference
- PM²-Leitfaden 3.1, Abschnitt 5.2
- Edition
- PM² Guide 3.1
Cite this entry
Project Initiation Request. (n.d.). In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/project-initiation-request/
Project Initiation Request (n.d.). PMDecoder, entry on PM²-Leitfaden 3.1, Abschnitt 5.2. https://pmdecoder.com/en/glossary/project-initiation-request/ (retrieved 24 November 2026)
@misc{projectinitiationrequest,
title = {Project Initiation Request},
note = {PMDecoder, PM²-Leitfaden 3.1, Abschnitt 5.2},
url = {https://pmdecoder.com/en/glossary/project-initiation-request/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/project-initiation-request/"> <p>First PM² artefact, formally recording a need, problem or opportunity together with the desired outcomes</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/project-initiation-request/">Project Initiation Request</a>, PMDecoder, PM²-Leitfaden 3.1, Abschnitt 5.2</footer> </blockquote>
Found a mistake? Let us know, we check every report.