Control or Monitor & Control?

closely related

Like the other terms, Monitor & Control means measuring progress and correcting deviations. In PM² it is a separate group of activities spanning all phases.

Comparison of Control and Monitor & Control
ISO 21506ControlPM²Monitor & Control
What it coversOngoing comparison of the project's status with the plan and initiation of action when variances put the objectives at risk.In PM², the activities spanning all phases with which the Project Manager measures performance, detects deviations and takes corrective action
Equivalent in PRINCE2Progress practice closely relatedProgress practice closely related
To the term pageControlMonitor & Control

All designations of this concept side by side