Team Plan
Definition
In PRINCE2, the team plan is the lowest planning level. It is produced by the team manager to plan the work on accepted work packages: which activities are needed, who carries them out, when the products will be finished and what effort is involved. Whether team plans are used and in what form depends on the project; they are not mandatory. If an external supplier works according to its own procedures, its team plan may be in its own format. In agile environments, a team’s planning, for example in iterations and backlogs, can take on the role of the team plan.
Equivalents in other frameworks
No equivalents have been recorded for this term yet.
Distinction
The stage plan belongs to the project manager and covers a whole stage; the team plan belongs to the team manager and relates to the work of that team. The work package defines what is to be delivered; the team plan describes how the team organizes delivery. It partly overlaps with a schedule in the general sense.
In practice
As part of a relaunch project, an agency takes on the work package “Visual style and photo production”. In her team plan, the team manager schedules four shooting days, image selection with the client and post-production, assigns the tasks to three people and sets internal checkpoints. The project manager receives only the handover dates and the weekly updates.
Frequently asked questions
Does the project manager have to approve the team plan?
Not necessarily. What matters is that the team manager and the project manager agree that the work package can be delivered with the plan within the agreed tolerances.
When is a team plan produced?
When the team manager accepts a work package, often earlier, so that the team’s estimates can feed into the stage plan.
Source and context
- Reference
- PRINCE2 7, Praktik Pläne
- Edition
- PRINCE2 7
- Author
- Dennis Hain
Cite this entry
Hain, D. (n.d.). Team Plan. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/team-plan/
Hain, D. (n.d.): Team Plan. PMDecoder, entry on PRINCE2 7, Praktik Pläne. https://pmdecoder.com/en/glossary/team-plan/ (retrieved 24 November 2026)
@misc{teamplan,
author = {Hain, Dennis},
title = {Team Plan},
note = {PMDecoder, PRINCE2 7, Praktik Pläne},
url = {https://pmdecoder.com/en/glossary/team-plan/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/team-plan/"> <p>Optional PRINCE2 plan used by a team manager to plan and control the work on one or more work packages.</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/team-plan/">Team Plan</a>, PMDecoder, PRINCE2 7, Praktik Pläne</footer> </blockquote>
Found a mistake? Let us know, we check every report.