Work package or Work Package?
closely related
In PRINCE2, a Work Package is, like a work package, a unit of project work. It is above all an agreement between project manager and team manager on delivery.
| PMI / PMBOK GuideWork package | PRINCE2Work Package | |
|---|---|---|
| What it covers | Smallest unit in the WBS: a clearly bounded partial result with one owner, for which effort, cost and duration are planned. | In PRINCE2, the agreed transfer of responsibility for delivering specific products from the project manager to a team manager. |
| Equivalent in ISO 21506 | Work package equivalent | Work package closely related |
| To the term page | Work package | Work Package |