Sensitivity analysis
Definition
Sensitivity analysis changes one uncertain variable after another, such as material prices, the duration of a permit procedure or sales volumes, and observes the effect on cost, schedule or economic viability. This reveals which variables are particularly critical and where more accurate estimates or responses are most worthwhile. The result is often shown as a tornado diagram, with the most influential variables at the top.
Equivalents in other frameworks
No equivalents have been recorded for this term yet.
Classification
- this term
- Sensitivity analysis
- Topic area
- Risks and opportunities
Distinction
Monte Carlo simulation varies all variables randomly at the same time; sensitivity analysis usually varies one after another. Scenario analysis combines several changes into coherent pictures of the future, such as a favourable and an unfavourable case. Sensitivity analysis does not assess probabilities, only the strength of relationships.
In practice
For the economic appraisal of a solar park, a project developer changes five variables by ten per cent each. The net present value reacts most strongly to the electricity price, followed by financing costs; construction costs come only third. The team therefore concentrates on concluding a long-term power purchase agreement instead of spending more weeks optimizing the construction tender.
Frequently asked questions
What does a tornado diagram show?
A horizontal bar for each variable examined, whose length indicates the range of its effect. The longest bars are at the top, producing a funnel shape.
What are the limits of sensitivity analysis?
It usually looks at variables individually and overlooks interactions, for example when rising prices and longer durations occur together.
Source and context
- Author
- Dennis Hain
Cite this entry
Hain, D. (n.d.). Sensitivity analysis. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/sensitivity-analysis/
Hain, D. (n.d.): Sensitivity analysis. PMDecoder. https://pmdecoder.com/en/glossary/sensitivity-analysis/ (retrieved 24 November 2026)
@misc{sensitivityanalysis,
author = {Hain, Dennis},
title = {Sensitivity analysis},
note = {PMDecoder},
url = {https://pmdecoder.com/en/glossary/sensitivity-analysis/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/sensitivity-analysis/"> <p>Examination of how strongly the outcome of a project changes when individual input variables are changed</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/sensitivity-analysis/">Sensitivity analysis</a>, PMDecoder</footer> </blockquote>
Found a mistake? Let us know, we check every report.