Monte Carlo simulation
also: Monte Carlo analysis, Monte Carlo method
Definition
In a Monte Carlo simulation, uncertain variables such as activity durations or cost items are entered not as fixed numbers but as distributions, for example based on three-point estimates. The computer randomly draws a value for each variable, calculates the result and repeats this run many thousands of times. All the results together form a distribution that shows the probability of meeting a particular date or budget.
Equivalents in other frameworks
No equivalents have been recorded for this term yet.
Classification
- this term
- Monte Carlo simulation
- Topic area
- Risks and opportunities
Distinction
The critical path method calculates with fixed durations and produces exactly one end date; the simulation produces a range with probabilities. Sensitivity analysis shows which input variables influence the result most and is often evaluated together with the simulation. The name alludes to the casino in Monte Carlo, because the method works with random numbers.
In practice
A construction company is to commit contractually to a completion date for a multi-storey car park. The simulation, with ranges for 45 activities, shows that the planned date will be met with a probability of only 30 per cent, and a date six weeks later with 80 per cent. The company offers the later date and uses the distribution to show the client why an earlier date would very probably trigger contractual penalties.
Frequently asked questions
How many runs does a simulation need?
A few thousand is usual. Beyond that number, the results generally hardly change.
Is the simulation more accurate than normal planning?
It is more honest, because it makes uncertainty visible. Its accuracy, however, depends entirely on the ranges and dependencies entered.
Source and context
- Author
- Dennis Hain
Cite this entry
Hain, D. (n.d.). Monte Carlo simulation. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/monte-carlo-simulation/
Hain, D. (n.d.): Monte Carlo simulation. PMDecoder. https://pmdecoder.com/en/glossary/monte-carlo-simulation/ (retrieved 24 November 2026)
@misc{montecarlosimulation,
author = {Hain, Dennis},
title = {Monte Carlo simulation},
note = {PMDecoder},
url = {https://pmdecoder.com/en/glossary/monte-carlo-simulation/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/monte-carlo-simulation/"> <p>Computational method that runs a project model thousands of times with randomly drawn values to determine probabilities for dates and costs</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/monte-carlo-simulation/">Monte Carlo simulation</a>, PMDecoder</footer> </blockquote>
Found a mistake? Let us know, we check every report.