Project Brief or Project mandate?

partially overlapping

Like a project charter, the PRINCE2 Project Brief describes a planned project. It is a basis for the decision to start initiation, not an authorization.

Comparison of Project Brief and Project mandate
PRINCE2Project BriefISO 21506Project mandate
What it coversPRINCE2 management product describing a planned project in enough detail for the project board to decide whether initiation may begin.Document that formally puts a project into effect and grants the project manager their authority.
Equivalent in PMI / PMBOK GuideProject charter partially overlappingProject charter equivalent
To the term pageProject BriefProject mandate